Evacuation and Muster Plan For
Pilot House Roof Project #2009
32 Atlantic Ave Boston, MA 02110
An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire). Person/persons discovering emergency shall take the following actions:
- Immediately dial 911
- Contact Consigli Superintendent: John Dudek (774)573-8054
Evacuation order shall be:
- Alerting all workers by the sounding of three long blasts of an air horn or building alarm.
- Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
- Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
- Portable fire extinguishers are provided if fire is in incipient/budding phase only.
- Superintendent, Jon Dudek, and any other trained individual on site, is responsible for performing first aid on any injured person once outside evacuated area.
- After an emergency evacuation, employees are directed to gather on the lawn on the North West elevation of the building.
- Superintendent John Dudek, or a CCC designee, will be responsible for accounting for all CCC employees on site.
- Superintendent John Dudek, or the CCC designee, will be responsible for knowing which subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Dudek or the CCC representative.
- For further assistance with emergency evacuation procedures, you may contact Safety Director Dan Della-Giustina at (508)686-6008.
Muster Point
Back– End of Evacuation and Muster Plan