Site Specific Safety and Health Program

Dana Farber Cancer Inst. Merrimack Valley Renovation

5 Branch St. Methuen, MA 01844

Project # 1967

 

Emergency Response Plan

EMERGENCIES SHOULD BE REPORTED BY CALLING 911

SITE INFORMATION 

This Emergency Response Plan (E.R.P.) is specifically developed for Consigli Construction work associated with the DFCI Merrimack Valley Renovation Project.

SITE LOCATION

The construction site is located at 5 Branch St. Methuen, MA.01844 The location for the project field office is currently at the Project jobsite (notifications of any changes will be provided).  If necessary, the field office will become the Emergency Operations Center (EOC).

EMERGENCY TYPE

The following situations are considered emergency response actions and should be handled in accordance with the procedures outlined in this plan.

  • Serious Injury/Fatalities
  • Fire/Explosion
  • Structural Damage/Collapse
  • Weather or Geological  Event
  • Environmental Incident
  • Traffic Disruption
  • Utility Damage
  • Illegal Activity
  • Labor Problems
  • Bomb Threats/Military Ordinance Unearthing
  • Acts of Terrorism

When reporting an emergency, please provide the following:

• Your location, phone number, and name;

• The location of the incident (building name, floor and room number);

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);

• The safest route to the incident

Crisis Response Protocol:

  • Attend to the injured
  • Immediately contact Dan Della-Giustina (508)686-6008
  • Post person at front gate, only allow access to emergency responders
  • Record names/addresses of witnesses
  • Do not allow media on site
  • Refer all media inquiries to the Milford office (Amy Bowen )

A Consigli designated individual shall wait at the main construction site entrance to escort Emergency Services personnel as they arrive.

The following is a list of the Chain of Command/Call Hierarchy on the project for establishing lines of succession during communication involving all emergencies.

Back End of Emergency Response Plan

 

Emergency Contact Names and Numbers

1. First call:  911 Fire or Police

2. CCC Superintendent: Todd Flanders (774)217-2349

3. CCC Senior PM: Sean O’Keefe (617)388-1239

4. CCC Gen. Supt.: Mike Caputo (774)248-0412

5. CCC Asst. Supt.: Todd Stafford  (774)278-3826

6. Corporate Safety: Dan Della-Giustina (508)686-6008

7. Safety Manager: Eddy Pellerin  (508)962-3974

Owner Representative

Vamshi Thakkallapalli, Project Manager (401)481-5693

Back End of Emergency Contact Names and Numbers

 

Medical Facilities

Caritas Holy Family Hospital

70 East St , Methuen, MA 01844

(978)687-0151

Environmental Consultant

TRC   (781)933-2555 

300 Wildwood Avenue Woburn, MA  01801

Robert Thomson, Field Ops.Supervisor                                       

Emergency Protocol In case of emergency a Consigli representative will be dispatched to the Main entrance of the building to meet the responding Emergency Personnel and advise the individual in charge of the location of any chemicals or hazardous substances that may be present on any of the floors. SDS sheets will be readily available if needed by the Fire Dept.

In the event of a serious injury requiring the assistance of EMS the injured worker will be kept as comfortable as p ossible.  Emergency first aid if necessary will beadministered.  Under no circumstances will the injured person be moved unless the worker’s life is in danger because of fire or calamity.  A worker will be assigned to meet the medical personnel at the above location to direct them to the location of incident.

In the event an evacuation is required all personnel at this job site will assemble in the identified Muster Point highlighted on the “Evacuation Plan”. The foreman for each company will meet at that location and take a head count of their crew and report to Consigli Superintendent. If for some reason a worker is unaccounted for, the fire department will be notified of the last location where the worker was observed.

Back End of Medical Facilities

 

Site Safety Plan

Scope of Proposed Operations:  This project has a start date of Mid December 2018 with an expected finish of October of 2019.   Project hours will be between 7:00am and 3:30pm Monday through Friday unless otherwise approved by Consigli Construction. The building is a vacant 3 story structure that Consigli will gut and renovate into a medical facility for Dana Farber.  That being said, Consigli’s scope will be limited to demolishing 50% of the first floor and 100% of the third floor and fitting both aforementioned areas out. 50% of the first floor and all of the 2nd floor will be left as is other than some floor penetrations for mechanicals. The scope for this project consists of a full interior renovation and MEP upgrades for the creation of a new 45,000 sq. ft. (30,000 sq. ft on third floor and 15,000 sq. ft. on first floor) medical facility. This work will involve interior demolition of much of the existing mechanical systems, walls, ceilings, and floors. Any underground work will take place within the footprint of the building to install new plumbing.  Steel dunnage will be added to the roof for the installation of new Air Handing Units (AHU). The existing façade will remain as is. Interior fit-out will complete the project with partitions throughout and new interior finishes (paint, floor, lighting, etc.). 

PURPOSE: The purpose of this Site-Specific Safety and Health Program is to illustrate Consigli’s approach to identifying project specific hazards and controls and how said risk is managed through a comprehensive Safety and Health Program.

S.A.F.E.: Staying Accident Free Every Day is the Safety Mission that forms the very foundation of the Consigli Safety Culture.  The S.A.F.E.  mission, which is supported by technology, (Predictive Solutions internal auditing instrument  which identifies and defines leading indicator related information); Leadership (Empowering our team members to assure safe projects); Humanization (Protect the ones you love by protecting yourself); Jobsite Gym (Morning warm-ups, jobsite gym); Training (Integrating sub-contractors into the Consigli Safety Culture); and Lean (nothing hit the ground), is the driving force behind Consigli’ s drive to our vision – ZERO.  ZERO is the philosophy that all accidents are preventable, and that no accident is acceptable. The S.A.F.E. mission is the guiding force to achieving the Consigli Safety Vision which is ZERO.  

Identify the specific route in and out of the construction site (Traffic Management): All deliveries and waste removal shall be done using the construction freight elevator and could possibly include the removal of a window with trash chute to a dumpster as well. Deliveries need to be coordinated with Consigli superintendent with at least a 48-hour notice.  All contractors will be responsible for adhering to Consigli’s restrictions and regulations regarding driving, parking and the delivery of materials. Parking will be designated within the project site (existing parking lot).

Designated work hours (any work outside these hours must have prior CCC approval):  All work shall take place during business hours, Monday – Friday 7:00am to 3:30pm, any work which may  need to take place outside of these hours will need to be approved by the CCC Superintendent.

Activity Hazard Analyses (AHA) /Job Safety Analyses (JSA):  An AHA/JSA shall be conducted for each definable feature of work to be performed.  The AHA/JSA shall be submitted to the Consigli superintendent.  AHA’s and/or JSA’s shall be completed  and reviewed weekly by the foremen, discussed and signed by all workers, and posted accordingly where work is being performed.    

Demolition:  It should be noted that ½ of the 1st floor and the entire 3rd floor will be gutted Prior to the start of demo operations.  All demo is considered selective with no structural demo anticipated. Before preforming demo Consigli will need to confirm that all utilities leading into the area have been made safe.  The electrician will disconnect and lock out all electrical, the plumber will do the same with any plumbing lines, and the HVAC subcontractor will do the same on the HVAC piping and duct work.  Lock out tag out will be reviewed during the pre-construction safety meetings to assure disconnect and responsibility for protection of existing utilities is safe for any construction activities to commence. In spaces where some electrical or mechanical must remain live, a color coding system will be utilized for easy identification of live utilities that must stay active and utilities that must be removed.  Any and all utilities spray painted Red are not to be touched and need to be protected during operations. Utilities spray painted Green are to be removed as part of the selective demolition process only after lock-out/tag-out has been confirmed and utilities tested. If any utilities are unmarked, they shall be considered live.  Consigli/Riggs will be responsible for completing the Consigli demo checklist prior to the start of  work in the target areas.

Excavations:  Interior slab demo and excavations will be required for plumbing installation.  Any slab demo/cutting will be done only after GPR or X-Ray scanning is done to locate and mark any in-slab utilities.  Limited exterior excavation will be necessary for connection to existing water service. Any required permitting will be obtained before any excavating is to begin. Although no deep excavations are anticipated, it should be noted that should any excavation takes place that:  . 

  1. A Dig Safe Notification – dig safe number will be obtained and posted in the site office.
  2. Jackie’s Law (520CMR 14.00) will be strictly adhered to and permits must be obtained.  A copy will be posted in construction office.
  3. Copies of shoring engineering and tabulated data sheets for all trench boxes or other shoring/shielding systems brought on site will be provided to CCC and be kept in construction office.

**Review Chapter 19 for more detail**

Fall Protection: All workers exposed to a fall of 6′ or greater shall be protected by guardrails safety nets or personnel fall arrest systems. This is to include, but is not limited to, steel erection work on the roof, roofing, and any scaffold erection and dismantling. Floor holes will be protected by covering with acceptable material (3/4 plywood ½ steel) which must be secured and marked “hole”.  It shall be capable of supporting 2x the intended axle load of any equipment. Covers will stay in place until the hole/penetration has been filled.   

Any building perimeter openings are to be protected with a cable guard rail system or secured 2×4’s. Cables, if used, shall include turnbuckle for all straight runs.

Before any work is to begin on the roof it must be determined what method of fall protection will be implemented. All workers working on a roof shall have fall protection at all times. Roof flagging must be set up for all trades working on the roof. Flagging is to be installed at six feet from the edge for roofers, and 15 feet for all other trades. Whenever roofers and  other trades are on the same roof then the flagging must be pulled back to the maximum 15’ distance. 

The use of safety Monitors is not allowed!!!

**Review Chapter 13 for more detail**

Work on Ladders: All work on step ladders/straight ladders will be done in adherence to manufacturer’s recommendations.  Any worker who is on a step/straight ladder and could be exposed to a fall greater than the height of their work on the ladder will be required to install a form of fall protection. Step ladders will not be used as a form of access to a walking /working level, also all straight ladders will be tied of when installed for use.  Only ladders with a rating Type 1A or 1AA will be allowed on Consigli projects.

 Scaffold and elevated work platforms:  Expected scaffold needs are rolling 6’ “baker” scaffolds and possibly pipe scaffold. All scaffolds supported frame, pipe staging and Aerial lift platforms will be inspected daily before each shift by a competent person designated by each individual contractor who will be using it.  Said inspection will be documented on Inspection tags located at the stair tower/access point to each section… A scaffold checklist guide will be provided by CCC to each sub-contractor’s designated persons (upon request) to aid them with their daily inspection. All contractors who will erect scaffold will provide CCC with certification/qualification of scaffold erection training as well as an erection/dismantling plan. Fall protection is required 100% during erection/dismantling. Overhead protection will be provided for all access points at any buildings which are located under any form of scaffolding. Mobile scaffold fall protection is required at 4’. Mobile staging with a work platform with a height to base ratio greater than two to one will require outriggers. All scaffolding that is procured by CCC and is over 15’ in height will require that the CCC Safety Department review the scaffold prior to it being turned over for use by tradesmen. 

** Please review chapter 14 for additional details.**  

Aerial/Scissor Lifts:  Aerial and Scissor lift use is expected for interior MEP installations.   When aerial lifts are utilized, floor conditions and load rating will need to be reviewed in the intended work area.  Additionally the area shall will be inspected for overhead power lines, sink holes, covers, or any other unsafe conditions which could cause incident.  Aerial lift platforms will be inspected daily before each shift by a designated competent person designated.  All who will be performing work from an aerial lift will show documented proof of training prior to using the lift. Workers will be tied off at all times when using an aerial lift.

HazCom/Global Harmonization:  All Materials and chemicals used on-site shall have Safety Data Sheet (SDS) provided before being brought onsite.

  • SDS sheets on file in Consigli Construction’s Site Safety Plan
  • All SDS sheets shall be readily accessible.

** Please review chapter 20 for additional details.**  

Fire Protection: A detailed fire protection plan has been developed by Consigli along with the building owner for this project and will be onsite for review at all times.  The Plan involves:

  • New fire protection branch lines and quick-response sprinklers will be installed as part of the new renovation/fit-out scope. Once tied into the existing risers and tested per NFPA 13, the temporary heat detector loop will be removed.

  • Other fire alarm upgrades (such as horn/strobes, smokes detectors, fire dampers, etc.) will also be installed per the engineer’s design to suit the new floor layout(s).

  •  Sullivan & McLaughlin (Elec. License #17341A & 16609) will be installing the heat detector loop.

JC Cannistraro (Spr. Fitter License #SC-124663) will be cutting/capping the existing FP lines.

Consigli will develop and submit a project NPFA 241 plan that addresses life safety   areas of concern during the project as well as identifying the Fire Protection Program Manager (FPPM).

  • Any hot work will also follow the guidelines of the state building codes, local requirements, and those established within the Consigli hot work policy which requires permits for all hot work(including sign-off by a certified fire watch).

  • The entire building (including the first and second floors) is currently unoccupied. The owner is aware ofthe plan regarding the fire protection alterations as outlined here.

A Hot Work Permit will be required for any activity that generates heat, sparks or has an open flame. This will be coordinated through  Consigli and Methuen Fire. (if required).   Any hot work will stop one hour before the regular end of the day work stoppage. Flammables will not be stored inside the building or left overnight on the scaffold or in the building.  All combustible or flammable materials will be stored in an appropriately rated lockable cabinet located no closer than 50 feet from the nearest structure. Fire extinguishers will be provided for every 3000 square feet.  They will be installed on job made stands and conspicuously located throughout.  They will be part of the daily inspection with extinguisher log completed monthly.  Storage of any acetylene cylinders will be done in a secure and upright area, with good ventilation.  This will be a strict no smoking project. All penetrations leading outside of the construction area will be fire stopped using approved fire rated material prior to the end of each shift.

**Review Chapter 17 for more detail**

Electrical: All electrical tools, cords and equipment must be in good working order. To that end, all electrical tools and components must be visually checked on a daily basis.  Any tools with damaged cords or damaged cords must be taken out service… All cords must be equipped with a ground pin, flat three wire cords are not allowed.  SJO and SJT or other similarly rated cords only shall be used.  The electrician will be responsible for all temp power and any temp lighting that may be needed.  They will coordinate all lock out tag out procedures. All temporary power for the project will be installed on protected and dedicated circuits with 100% GFCI protection.  GFCI will be tested by the electric contractor weekly to assure proper function with a log book filed with CCC monthly.  No live electrical work will be conducted.  No live electrical work will be conducted per NFPA 70E.

**Review Chapter 26 for more detail**

Utility Exposures: Any overhead power lines will be located and identified prior to use of any equipment (Cranes) which may come in to contact with them. All sidewalks will be protected if equipment is to be driven over them. Utility’s direct buried will be marked out. At no time will lifts be set up in this area

Crane:  Mobile cranes are expected for lifting of HVAC/RTU’s on roof as well as for placement of steel for penthouse. All cranes will require independent annual 3rd party inspections and will be utilized for operation only after detailed lift plans are submitted.   It is anticipated that these cranes will all be hydraulic.  In the event that a lattice boom crane is utilized, then the crane must get an on-site 3rd party inspection once the crane is assembled, prior to operation.

There is a requirement to assure that certified riggers, signalmen, and crane assemblymen are utilized.  All picks are to be done by a licensed operator.  As previously mentioned, a detailed pick plan will be required to assure that no picks are critical in nature.  Critical picks are defined as those involving 2 cranes lifting simultaneously, a pick that is over 75% of capacity, a pick that involves the lifting of a man basket, or any other lift that is deemed to involve special conditions.  Location and set up will be reviewed with crane operator prior to set up and pick. All lifting operations will require that the operator and any involved contractors follow the steps listed below as well as in CCC Crane Safety policy.

1. All Hoisting equipment will have an up to date 3rd party inspection certificate with the equipment which will be copied and filed in the office trailer.

2.All lattice boom cranes will have an independent 3rd party inspection completed each time one is set up on the project, after assembly and prior to operation.

3. All equipment operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the Commonwealth of MA.

4. All underground vaults and existing utilities will be marked before as well as before any crane is set up.

5. Documented rigging equipment inspections.

6. Documented daily crane inspections filed with CCC weekly.

7. Documented rigger and hand signalman training will be provided.

8. Crane work will be scheduled on Saturdays as much as possible to limit their impact

** Please review chapter 24 for additional details**  

Equipment issues: All operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the Commonwealth of MA.  All safety devices and warning alarms must be in good working order and all leaks are to be repaired immediately.  All equipment will be used in accordance with the manufacturer’s recommendations for safe usage and have its operators manual as well as an extinguisher with it at all times.  Subcontractors who will have equipment on site will be responsible for having a spill kit available at all times.

** Please review chapter 24 for additional details**

Confined Space:  A written plan will be needed to work in any tanks/vaults and crawl spaces during this project which have been designated permit confined spaces by CCC, this plan must include air monitoring.

** Please review chapter 21 for additional details.**  

Designated First Aid Plan:   All injuries no matter how minor must be reported to Consigli Superintendent immediately. The superintendent will then report all injuries to the CCC Safety Director and Claims Manager.   A fully stocked first aid kit and blood borne pathogens kit shall be maintained on the project site.  Only properly trained personnel will administer first aid.  Consigli Construction shall follow Site Safety Plan for first Aid.  Report any incidents to the Safety Director

** Please review chapter 1 and 27 for additional details.**  

Substance Abuse: As a condition of employment, all Consigli personnel are required to submit to a urinalysis test for determination of the presence of illegal substances.  A positive result will disqualify the applicant for employment on this project.

Evacuation Plan (RACE, and Routes of Egress): Please refer to the Evacuation Plans attached. All Consigli employees shall attend the Project Safety Orientation. Consigli Construction’s Job Supervisor will conduct a safety orientation talk to each employee and subcontractor to site specific fire safety protocols.

Emergency Management Response: In the event of an Emergency the construction workers shall leave the building immediately. Point of assembly/muster shall be located at the MUSTER POINT sign as identified on the “Evacuation Plan”.  During any significant event  the Superintendent shall instruct the construction workers to leave the site or remain in place and await further instruction. 

When reporting an emergency, please provide the following:

• Your location (5 Branch St Methuen, MA) phone number, and name;

• The location of the incident (building name, floor and room number);

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);

• The name and amount of the material spilled (if applicable); 

• The safest route to the spill (if applicable).

** Please review chapter 8 for additional details.**  

Personnel Protective Equipment (PPE):  All CCC and sub-contractor workers will wear hard hats and safety glasses at all times.  All CCC personnel performing work with their hands shall be required to wear gloves that are appropriate to the task.  When not performing actual work with their hands, workers will be required to have gloves available for immediate use. Face shields will be required for all personnel who are performing overhead work, using metal chop saw or any type of metal grinding. All welders will be required to have hard hats with integral welding shields.

Restricted Areas:  Contractors are prohibited from entering any adjacent areas of the project site unless work has been previously authorized and scheduled.  It is important that workers do not park in/in front of adjacent driveways during construction.  All workers will try to limit their impact on surrounding areas.

Lean Requirements:  No materials shall be delivered to the site earlier than 3 days before said materials are to be installed/put into place.  If materials have to be delivered before that 3 day time period, subcontractor shall get prior approval from Consigli Superintendent. Because of this, notification / scheduling is required for all deliveries to the site. Subcontractors must notify Contractor at least 24 hours in advance. Contractor has the right to refuse any deliveries not properly scheduled or due to logistical constraints as necessary .All subcontractors’ delivered materials shall be placed on wheeled carts, wheeled racks or in wheeled bins so as to necessitate easy relocation in the event materials need to be moved.  Carts, racks, or dollies shall not exceed manufacturers intended weight loads.  Materials/tools can be delivered and stored on pallets only if pallet jacks are delivered simultaneously with said delivery to provide for ready mobility.  Additionally, pallet jacks need to remain in immediate area. Each subcontractor will need to supply their own pallet jacks for their own materials and keep their pallet jack within reasonable distance at all times.All work stations shall be provided with wheeled trash bins for immediate placement of all debris produced as a part of the subcontractors operations. 

All trash will be immediately placed in wheeled containers provided by Consigli. All subcontractors shall use rubber wheeled carts when moving material or removing trash from a building.  Any damage caused by the Subcontractor shall be repaired at the cost of the Subcontractor.  Back charges will be appropriately assessed for the cost of the repairs.  No trash or materials shall be left on the floor.  Subcontractors shall, where feasible, elevate all electrical extension cords, hoses, or cables – removing them from all walking/working surfaces.  Electrical Cords, when elevated shall be supported or suspended in a manner that does not subject them to damage.  Storage of delivered materials in cardboard containers shall be discouraged. When materials must stay in cardboard containers, said containers shall be removed from the projects immediately after product is unpacked. 

Subcontractor will participate in schedule development meetings as required by Consigli

Minimum Site Safety Requirement:  All Consigli workers, and any subcontractors, shall have, at a minimum, an OSHA 10 Hour Construction Safety Outreach training certificate and shall provide documentation of training.

Materials Management: Materials management, getting materials into and out of the project, will be done through existing entrances and the freight elevator. Getting materials into and out of the project will be a challenge that needs to be adequately planned. All deliveries are to be scheduled with the CCC Superintendent. A comprehensive Activity Hazard Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed in a reasonable amount of time will be delivered to the site. Attention must be paid to structural analysis in regards to loading existing floors with material and equipment

Steel Erection: Steel erection will be necessary for the placement of framework for the Penthouse.  All iron workers will be required to use fall protection at 6′. The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations..

** Please review chapter 16 for additional details **

Back End of Site Safety Plan

 

Environmental Emergency Contact and Management Response

Consigli identified Emergency Response Subcontractor;

Name:  Cyn Environmental Services, Inc. (781)341-1777

100 Tosca Drive Stoughton, MA 02072.

Asbestos: A Hazardous Materials report has been prepared by TRC.  The complete table and “List of Materials tested, Quantities, and Locations” can be found with the hazardous material report. This does not mean that asbestos or suspect asbestos containing materials  could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately. All identified asbestos will be fully abated by a licensed and regulated asbestos abatement contractor under a formal plan to be written, submitted and in accordance with the DEP.

IT IS THE RESPONSIBILITY OF ALL SUBCONTRACTOR FOREMEN TO REVIEW THE HAZARDOUS MATERIAL REPORT & CORRESPONDING ABATEMENT REPORT WITH THEIR WORKERS.  A copy of the hazardous Material/abatement report will be on site at all times and available to anyone request it. All work and disposal will be done in compliance with state and federal regulations and standards. All workers on this project must have completed Asbestos awareness training prior to starting on this project.

Lead:  With the building being built in 1988 there is a low likelihood that there is any lead paint.  One exception would be any structural steel that may be in the building.  If that is impacted in any way a sample will need to be taken.

Silica: Any activity which can produce silica dust will use engineering controls to keep dust to a minimum.  A written exposure plan must be developed for all silica producing tasks that clearly defines the following:

1) A description of the tasks in the workplace that involve exposure to respirable crystalline silica;

2) A description of the engineering controls, work practices, and respiratory protection used to limit employee exposure to respirable crystalline silica for each task;

3) A description of the housekeeping measures used to limit employee exposure to respirable crystalline silica 

4) A description of the procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to respirable crystalline silica and their level of exposure, including exposures generated by other employers.

There will be no dry cutting of any masonry material allowed; if water cannot be used then a dustless vacuum system consisting of HEPA dustless vacuum system will be used.  Prior to the project going full scale an exposure assessment of a worker grinding and cutting masonry while using the HEPA system an exposure assessment will be done so as to establish the silica exposure level. No respirators will be issued without the express consent of the Consigli Safety department.  Nuisance mask like an N95 if used will be on a voluntary basis and at no time will these types of mask be issued to the workers.

Polychlorinated Biphenyl’s (PCBs):  At this time there are no activity’s which are planned which would disturb any surface with suspect amounts of PCB’s… This does not mean that regulated levels of PCB’s could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately.

Light ballast unless labeled “No PCB’S” will be designated PCB containing, All PCB containing material shall be removed and disposed of in accordance with all local, state (MEMEP Special waste management rules 06-096-CMR 400) and federal regulations and be coordinated with the building owner.  All other inquiries or locations in regard to PCB containing material can be located in the Hazardous Material survey. If identified on any of the materials to be impacted, PCB ‘s will be abated. Any and all PCB remediation will be performed by a licensed /qualified contractor

** Please review chapter 29 for additional details**

Freon/Glycol: All Freon/Glycol materials will be removed from equipment and stored per manufacturer’s recommendations before it is disturbed, moved or removed.  All workers who will be working with the above mentioned materials must provide CCC with certifications or qualifications.  If not re-used, a disposal manifest will be provided to CCC.

Mold: Mold issues are not anticipated to be prevalent on this project, however if mold is discovered Consigli’s mold remediation policy will be implemented and followed.

** Please review chapter 22 for additional details **

Mercury: All fluorescent lamps/thermostats are presumed to contain mercury vapor, which is a hazardous substance. Mercury-containing lamps associated with fluorescent light fixtures in areas designated to be renovated will be treated accordingly.  All florescent bulbs removed during renovation will be collected, properly stored on site and given to the schools facility’s so as to be recycled or disposed of properly.

Noise: Noise exposure will be a concern so all operations must be coordinated with the Consigli Superintendent to limit any excess noise impact on the surrounding areas. All activity or task which may cause load noise will be restricted as needed so as to limit the impact on surrounding workers.  

IAQ (indoor air quality): This is not an occupied renovation so an IAQ program is not necessary.

**Please review chapter 29 for additional details**

Planning:  The project team will meet with the subcontractors before the project start to review any site specific safety and health requirements. The project team shall be an integrated mix of owner, architect, engineer and Consigli Construction personnel.  If, after reviewing programs and meeting with the individuals, the team is satisfied with the risk control direction, personnel will be permitted to begin work. 

 

 

Back End of Environmental Emergency Contact and Management Response