Site Specific Safety and Health Program

NRC – 100 Chestnut St.   
100 Chestnut St. Somerville, MA 02143

Project # 2597

 

 

Emergency Response Plan

SITE INFORMATION

This Emergency Response Plan (E.R.P.) is specifically developed for Consigli Construction work associated with the NRC-100 Chestnut Project located at  100 Chestnut St. Somerville, MA.

SITE LOCATION

The address for project is 100 Chestnut St. Somerville, MA 02143. The location for the project field office will be the office trailer located onsite. (notifications of any changes will be provided).  If necessary, the field office will become the Emergency Operations Center (EOC) for construction related activities.

EMERGENCY TYPE

The following situations are considered emergency response actions and should be handled in accordance with the procedures outlined in this plan.

  • Serious Injury/Fatalities
  • Fire/Explosion
  • Structural Damage/Collapse
  • Weather or Geological Event
  • Environmental Incident
  • Traffic Disruption
  • Utility Damage
  • Illegal Activity
  • Labor Problems
  • Bomb Threats/Threats of Violence
  • Acts of Terrorism

The following is a list of the Chain of Command/Call Hierarchy on the project for establishing lines of succession during communication involving all emergencies.

Back End of Emergency Response Plan

 

 

Emergency Contact Names and Numbers

1. First call: 911                                 

2. CCC Superintendent: George Regis Jr. (617)918-3341

3. CCC PM: Justin Billings (774)573-2284 

4. Bryan Kingsbury: Corporate Safety (508)808-9359

5. Dan Della-Giustina Jr. : Safety Manager (774)462-1481

 Additional Construction Contacts

  • CCC Project Engineer: Jason Chenevert (774)737-3542
  • CCC Assistant Super: Riley Smith (617)429-2936
  • CCC Project Executive: Darrin Ball (617)593-6735
  • CCC General Super: Steve O’Toole (617)293-6007
  • Owner Representative: Nat Wysor (617)904-7109

Local Non-Emergency Contact Information.

Somerville Police Department (non-emergency) (617)625-1600

Somerville Fire Department (non-emergency) (617)623-1700 x8101

MBTA Transit Police (617)222-1000

Back End of Emergency Contact Names and Numbers

 

 

Medical Facilities

OHS Total Care
1340 Soldiers Field Rd. Brighton, MA 02135
(866)510-3002

 

Mount Auburn Hospital
330 Mount Auburn St. Cambridge, MA 02138
(617)499-5025

A Consigli representative will be dispatched to the main entrance of the building (or work area, as necessary) to meet the responding Emergency Personnel and advise the individual in charge of the location of the incident and any chemicals or hazardous substances that may be present on any of the floors. Safety Data Sheets will be readily available if needed by the Fire Dept.

In the event of a serious injury requiring the assistance Somerville EMS, the injured worker will be kept as comfortable as possible.  If necessary, Emergency first aid will be administered.  Under no circumstances will the injured person be moved unless the worker’s life is in danger because of fire or calamity.  A worker will be assigned to meet the medical personnel at the site entrance to direct them to the location of incident.

In the event an evacuation is required all personnel at this job site will follow the building/site evacuation plan(s) and meet at the designated Muster Point (located at the field office (see below.)  Evacuation routes will be posted in the work area and will be updated as construction activities progress. The foreman for each company will meet at that location and take a head count of their staff and report to Consigli Superintendent. If for some reason a worker is unaccounted for, security/fire department will be notified of the last location where the worker was observed.

Construction Muster Point location

 

Back End of Medical Facilities

 

 

Site Safety Plan

Scope of Proposed Operations: The 100 Chestnut Core & Shell Project will begin in Spring of 2021. Project hours will be between 7:00am and 3:30pm Monday through Friday. All work performed outside of these designated times requires Consigli approval. The scope of the project is demolition and site improvements and the construction of a new building at 100 Chestnut St. in Somerville, MA.  Work on the project includes:

  • New construction of a 200,000 “2-down, 4-up” core and shell life science building.
  • Existing site is currently a multiple structures and parking lot.  1st phase is an enabling phase to demo existing buildings and relocate utilities that currently run through the site. 
  • Install and maintain site perimeter fence for public protection and access to adjacent properties, including temporary walkways and overhead protection. Logistical challenges to minimize impact to adjacent buildings.
  • MBTA impact will be limited but will apply when installing site fencing and test pits along the Northeast elevation of the site. 
  • Install a 2 levels down full perimeter slurry wall with concrete beam cross lot grade beams at depth to brace walls, steel whalers and cross lot bracing.
  • Deep mass excavation with foundation footings and walls.  
  • Steel structure 2 floors below grade and 4 levels above grade.
  • MEP design build and fire protection/life safety for core and shell.
  • Exterior façade metal stud framing waterproofing with metal panel, etc.
  • Roofing.

Purpose: The purpose of this Site Specific Safety and Health Program is to illustrate Consigli’ s approach to identifying project specific hazards and controls and describe how they are managed through a comprehensive Safety and Health Program.  This site specific safety plan will work in conjunction with the Consigli Safety Program as well as all applicable Somerville requirements. 

Contractor Orientation:  Upon arrival of all site crew members completion of the Consigli Construction site orientation, that will review all elements of the Consigli Safety Program, is required.  Once all orientation and initial training is completed Consigli hardhat stickers will be issued.

S.A.F.E.: Staying Accident Free Every Day is the Safety Mission that forms the very foundation of the Consigli Safety Culture.  The S.A.F.E. mission, which is supported by technology, (Predictive Solutions internal auditing instrument which identifies and defines leading indicator related information.) Weekly Predictive Solutions inspections will be uploaded to SCOPE; Leadership (Empowering our team members to assure safe projects); Humanization (Protect the ones you love by protecting yourself); Jobsite Gym (Morning warm-up stretch program); Training (Integrating sub-contractors into the Consigli Safety Culture); and Lean (nothing hit the ground), is the driving force behind Consigli’ s drive to our vision – ZERO.  ZERO is the philosophy that all accidents are preventable and that no accident is acceptable.  The S.A.F.E. mission is the guiding force to achieving the Consigli Safety Vision which is ZERO. 

Logistics/Access/Traffic Management: Main construction access will be restricted to routes pre-determined by the owner, Somerville, and Consigli. All contractors will be responsible for adhering to Somerville restrictions and regulations in regards to driving, parking and delivering materials. Strict adherence to posted speed limits and parking locations is required. Pedestrians will be given the right of way at all times. Parking will be designated in pre-determined contractor parking locations and reviewed during orientation.  Pedestrian access through the campus must be kept clear.   

Designated work hours (any work outside these hours must have prior CCC approval):  All work shall take place during business hours, Monday – Friday 7:00am to 3:30pm, any work which may  need to take place outside of these hours will need to be approved by the CCC Superintendent and the Project Management team.


Job Safety Analysis (JSA):
  A Job Safety Analysis (JSA) shall be conducted for each identifiable feature of work to be performed.  The JSA shall be submitted to Consigli superintendent/supervisor.  At a minimum the JSA shall be reviewed weekly.  More frequent review shall be necessary as tasks change.  The JSA shall be reviewed with all involved personnel performing that particular task and signed by all workers including their supervisor. 

Excavations: Excavations will be required for footing and foundation work.  Any ledge will require stabilization and fall protection at the upper grade.  All required permitting will be obtained before any excavating is to begin.  If necessary, tabulated data/engineering for shoring and shielding systems will be obtained and available on site at all times when in use. All excavations will be inspected by a competent person on a daily basis.  Written excavation inspections will be done if the excavation exceeds 5’. 

  • Dig Safe Notification/utility locator – number/report will be posted in office
  • City or Town permit requirements (DPW & Town Hall) if needed.
  • Jackie’s Law (520CMR 14.00) will be strictly followed and permitting will be

Obtained. A copy will be posted in construction office.

  • Soil onsite shall be pre-characterized for contaminants prior to any export from site.  Woodward & Curran is the site LSP (Licensed Site Professional)
  • Copies of soil engineering and tabulated data sheets for all trench boxes or other    shoring/shielding systems brought on site will be provided to CCC and be kept in construction office
  • This project will require the use of an installed, engineered Support of Excavation (SOE) system for the safe access to 2 levels of underground foundation work. 

**Review Chapter 19 for more detail

Demolition:  The scope of demolition for this phase is extensive.  With the removal of 3 buildings onsite (Building A, B, C.)

Prior to the start of demo operations, the contractor preforming demo will confirm that all utilities leading into the area have been made safe (cut/cap.) The electrician (utility) will disconnect and lock out all electrical, the plumber (DPW) will do the same with any plumbing lines, and the HVAC subcontractor will do the same on the HVAC piping and duct work.  Lock out tag out will be reviewed during the pre-construction safety meetings to assure disconnect and responsibility for protection of existing utilities is safe for any construction activities to commence. 

In spaces where some electrical or mechanical must remain live, a color coding system will be utilized for easy identification of live utilities that must stay active and utilities that must be removed.  Any and all utilities spray painted (or otherwise marked) Red are not to be touched and are need to be protected during all operations. Utilities spray painted Green are to be removed as part of the selective demolition process only after lock-out/tag-out has been confirmed and utilities tested.  If any utilities are unmarked, they shall be considered live until they are marked.  Any existing walls shall be removed using hand tools until investigation shows what mechanical systems are present behind the wall.  The demo contractor will be responsible for completing CCC demo checklist prior to the start of any work in their target areas. 

A demolition plan has been developed by the demolition contractor (JDC Demolition).


Fall Protection
: The work on this project will require work at height.  The majority of this work will be performed during deep excavation, foundations, steel erection, and roof work.  Fall protection will primarily be accomplished with the use of Personal Fall Arrest Systems (PFAS) and guardrails.  Other work at height may include work from scaffold platforms and ladders.  All fall protection for work performed on scaffolds will be required at a height of 6 feet or greater.  All scaffold erectors will maintain the ability to have fall protection by donning a harness and lanyard at all times during erection.  The roof will be reviewed for any leading edges and fall protection will be used/installed as required. 

Holes greater than 2” will be covered with acceptable material (3/4 plywood ½ steel) which will be secured and marked hole (cover must be able to withstand four times the intended load).  Covers will stay in place until the hole/penetration has been filled.  

**Review Chapter 13 for more detail

Work on Ladders: All work on step ladders/straight ladders will be done correctly per manufacturer’s recommendations.  Any worker who is on a step/straight ladder and could be exposed to a fall greater than the height of their work on the ladder (i.e. working by an open window or at a balcony edge.) will be required to utilize personal fall arrest system (PFAS) secure to structure overhead.  Step ladders will not be used as a form of access to a walking /working level, also all straight ladders will be secured when installed for use.  Only ladders with a rating Type 1A or 1AA will be allowed on Consigli projects.  Ladders use shall be reviewed in the JSA with alternative methods (scaffold, lift, etc.) considered to reduce hazards associated with ladder use.

Scaffold and elevated work platforms:  All scaffolds, supported frame, pipe staging and aerial lift platforms will be inspected daily before each shift by a competent person designated by each individual contractor who will be using it, which will be documented on posted inspection tags, or, in the case of lifts, on the inspection checklist.  A scaffold checklist will be provided by CCC to each subcontractors designated persons to aid them with their daily inspection. All contractors who will be erect scaffold will provide CCC with certification/Qualification of scaffold erection training as well as an erection/dismantling plan. Fall protection is required 100% during erection/dismantling. Overhead protection will be provided for all access points at any buildings which are located under any form of scaffolding. At a minimum, fall protection is required at 6’ on all scaffolds on Consigli projects. It is anticipated that a rolling “baker” style scaffold may be used on this project.  For mobile scaffolds on Consigli projects, the rules are stricter: guardrails are required at 4’. Mobile scaffolds with a work platform set at a height to base ratio greater than two to one will require outriggers.  Mobile scaffolds must have the wheels locked when in use.

** Please review chapter 14 for additional details.  

Aerial/Scissor Lifts: When lifts are to be used onsite, the area, slab, and/or ground conditions, in the intended work area, will be inspected for overhead power lines, sink holes, covers, or any other unsafe conditions which cause an unsafe incident. Scissor lift use is fully expected on the 3rd floor.  Aerial/scissor lifts will be inspected daily before each shift by a competent person designated.  All who will be performing work from an aerial/scissor lift will show documented proof of training prior to using the lift.  This training will be documented with the workers orientation paperwork.  Fall protection is required in the form of a PFAS is required in all aerial and scissor lifts and will be attached to the manufacturers prescribed anchor point.  If applicable, steel plates or equipment mats will be placed on the ground above any utility/ steam tunnel if there will be Aerial lifts operating on them. Workers will be tied off at all times when using an aerial lift.

Chemical and Materials/GHS:  All Materials and chemicals used on-site will have Safety Data Sheets (SDS) provided before being brought onsite.  Safety Data Sheets shall be available to all workers onsite for review.

  • All SDS shall be readily accessible.
  • SDS will be kept on file in Consigli Field Office
  • Labeling of materials will match the identifier on the SDS.
  • All workers will receive training as a part of their orientation as to the location of the SDS.

** Please review chapter 20 for additional details.  

Fire Protection: When hot-work is required the Consigli hot work permit program will be implemented.  During the Hot Work issuing process, alternative methods shall be reviewed to reduce the need for hot work activities.  The hot work program will be be coordinated through Consigli Construction and Somerville Fire (if needed.)  The Consigli “Hot Work Permit” will be completed prior to the start of any hot work.  All hot work will stop 60 minutes before the regular end of the day work stoppage.  A fire watch, equipped with a 10lb dry chemical extinguisher, will be used as necessary during hot work activities.

A NFPA 241 Construction Plan has been developed for the project and will be available for review as well as updated periodically. 

Flammables will not be stored inside the building or left overnight on the scaffold or in the building.  All combustible or flammable materials will be stored in an appropriately rated lockable cabinet located no closer than 50 feet from the nearest structure. Fire extinguishers will be provided for every 3000 square feet.  They will be installed on job made stands and conspicuously located throughout.  They will be part of the daily inspection with extinguisher log completed monthly.   All penetrations leading outside of the construction area will be fire stopped using approved fire rated material prior to the end of each shift. 

**Review Chapter 17 for more detail.

Electrical: All electrical tools, cords and equipment must be in good working order. To that end, all electrical tools and components must be visually checked on a daily basis.  Any tools with damaged cords or damaged cords must be taken out service… All cords must be equipped with a ground pin, flat three wire cords are not allowed.  SJO and SJT or other similarly rated cords only shall be used.  The electrician will be responsible for all temp power and any temp lighting that may be needed.  All temporary power for the project will be installed on protected and dedicated circuits with 100% GFCI protection.  GFCI will be tested by the electric contractor weekly to assure proper function with a log book filed with CCC monthly.  When existing power is used, a GFCI “pigtail” shall be added to the receptacle if not already equipped.  No live electrical work will be conducted.

**Review Chapter 26 for more detail

Cranes:  Crane use is expected on this project.  From “boom truck” delivery cranes, hydraulic cranes, to the lattice boom crane for steel erection and mechanical equipment, there will be cranes used for the work.  Cranes will require independent annual 3rd party inspections and will be utilized for operation only after detailed lift plans are submitted.   It is anticipated that these cranes will all be hydraulic.  In the event that a lattice boom crane is utilized, or in the case of the tower crane,  then the crane must get an on-site 3rd party inspection once the crane is assembled, prior to operation.

There is a requirement to assure that certified riggers, signalmen, and crane assemblymen are utilized.  All picks are to be done by a licensed operator.  As previously mentioned, a detailed pick plan will be required to assure that no picks are critical in nature.  Critical picks are defined as those involving 2 cranes lifting simultaneously, a pick that is over 75% of capacity, a pick that involves the lifting of a man basket, or any other lift that is deemed to involve special conditions.  Location and set up will be reviewed with crane operator prior to set up and pick.  All lifting operations will require that the operator and any involved contractors follow the steps listed below as well as in CCC Crane Safety policy.

 1. All Hoisting equipment will have an up to date 3rd party inspection certificate with the equipment which will be copied and filed in the office trailer.

2. All lattice boom cranes will have an independent 3rd party inspection completed each time one is set up on the project, after assembly and prior to operation.

3. All equipment operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the Commonwealth of MA.

4. All underground vaults and existing utilities will be identified before any crane is set up and their location shown on the crane lift plan.

5. Documented rigging equipment inspections.

6. Documented daily crane inspections filed with CCC weekly.

7. Documented rigger and hand signalman training will be provided.

** Please review chapter 24 for additional details.  

Confined Space:  A written plan will be needed to work in any tanks/vaults and crawl spaces during this project which have been designated permit confined spaces by CCC, this plan must include air monitoring.  Underground vaults are scheduled to be partially demoed during this work.

** Please review chapter 21 for additional details.  

Designated First Aid Plan:   All injuries no matter how minor must be reported to Consigli Superintendent immediately. The superintendent will then report all injuries to the CCC Safety Director and Project Management.  A fully stocked first aid kit and bloodborne pathogens kit shall be maintained on the project site.  Only properly trained personnel will administer first aid.  Consigli Construction shall follow Site Safety Plan for first Aid.   

** Please review chapter 1 and 27 for additional details.  

Substance Abuse: As a condition of employment, all personnel are required to submit to a urinalysis test for determination of the presence of illegal substances.  A positive result will disqualify the applicant for employment on this project.

Evacuation Plan and Routes of Egress: Please refer to the Evacuation Plans that are posted on the project.  All Consigli employees shall attend the Project Safety Orientation.  Consigli Construction’s Job Supervisor will conduct a safety orientation talk to each employee and subcontractor to site specific fire safety protocols.  The evacuation procedures will be covered during the Safety Orientation.  Routes of egress will be updated on the evacuation plans as construction activities require.

Emergency Management Response: In the event of an Emergency the construction workers shall leave all of the buildings immediately. Point of assembly/muster shall be identified on the posted evacuation plan.  In the Event of a DISASTER, the Superintendent or Safety director shall instruct the construction workers to leave the site or remain in place and await further instruction.  The following steps should be taken in the event of an emergency

When reporting an emergency, use 911
and provide the following:

• Your location (refer to site evacuation plan) phone number, and name;

• The location of the incident (building name, floor and room number);

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);

• The name and amount of the material spilled (if applicable); and

• The safest route to the spill (if applicable).

** Please review chapter 8 for additional details.   

Minimum Site Safety Training Requirements:  All Consigli workers, and any subcontractors, shall have, at a minimum, an OSHA 10 Hour Construction Safety Outreach training certificate and shall provide documentation of training.

Personal Protective Equipment (PPE):  All CCC and subcontractor workers will wear hard hats, safety glasses, high visibility clothing (lime green), safety toed shoes/boots, and gloves at all times.  All workers will wear hardhats and clothing that identifies the contractor employer and is clean and professional.  All personnel performing work with their hands shall be required to wear gloves that are a minimum of ANSI cut resistance level 6 or higher as required by the task (i.e. metal or glass work).   Face shields will be required for all personnel who are performing overhead work, using metal chop saw or any type of metal grinding.  All welders will be required to have hard hats with integral welding shields. 

Restricted Areas:  Contractors are prohibited from entering any adjacent areas of the buildings on the campus unless work has been previously authorized and scheduled.  It is important that workers do not park in/in front of adjacent driveways during construction or for deliveries.  All workers will try to limit their impact on surrounding areas.  Workers badges will be restricted to the level of training that they have completed. 

Lean requirements/Materials Management/Housekeeping: Getting materials into and out of the project will be a challenge that needs to be adequately planned.  All deliveries are to be scheduled with the CCC Superintendent.  A comprehensive Activity Hazard Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed within three days’ time will be delivered to the site. Attention must be paid to structural analysis in regards to loading existing floors with material and equipment. Movement of all materials over 8ft. will require 2 workers.

Listed below are additional Lean requirements

  • No materials shall be delivered to the site earlier than 3 days before said materials are to be installed/put into place.  If materials have to be delivered before that 3 day time period, subcontractor shall get prior approval from Consigli Superintendent.  Because of this, notification / scheduling is required for all deliveries to the site. Subcontractors must notify Contractor at least 24 hours in advance. Contractor has the right to refuse any deliveries not properly scheduled or due to logistical constraints as necessary.

  • All subcontractors’ delivered materials shall be placed on wheeled carts, wheeled racks or in wheeled bins so as to necessitate easy relocation in the event materials need to be moved.  Carts, racks, or dollies shall not exceed manufacturers intended weight loads.  Materials/tools can be delivered and stored on pallets only if pallet jacks are delivered simultaneously with said delivery to provide for ready mobility.  Additionally, pallet jacks need to remain in immediate area.    Each subcontractor will need to supply their own pallet jacks for their own materials and keep their pallet jack within reasonable distance at all times.

  • All work stations shall be provided with wheeled trash bins for immediate placement of all debris produced as a part of the subcontractors operations.  All trash will be immediately placed in wheeled containers provided by Consigli.  All trash bins shall be covered when not in use.
  • The wheel of rolling carts and bins shall receive be disinfected prior to entry into any clean environments. 

  • All subcontractors shall use appropriate equipment and wheeled carts when moving material or removing trash from a building.  Any damage caused by the Subcontractor shall be repaired at the cost of the Subcontractor.  Back charges will be appropriately assessed for the cost of the repairs.  No trash or materials shall be left on the floor. 

  • Subcontractors shall, where feasible, elevate all electrical extension cords, hoses, or cables – removing them from all walking/working surfaces.  Electrical Cords, when elevated shall be supported or suspended in a manner that does not subject them to damage. 

  • Storage of delivered materials in cardboard containers shall be discouraged.  When materials must stay in cardboard containers, said containers shall be removed from the projects immediately after product is unpacked. 

  • Subcontractor will participate in schedule development meetings as required by Consigli.

Back End of Site Safety Plan

 

 

Environmental Emergency Contact and Management Response

Consigli identified Emergency Response Subcontractor;

Name:  Cyn Environmental Services, Inc. (781)341-1777

100 Tosca Drive Stoughton, MA  02072 

Asbestos: A Hazardous Materials report has been prepared by the owner (Woodward & Curran Report Dated 12/10/2020) and all hazardous material will be abated prior to work commencing in affected areas (demolition.)

This does not mean that asbestos could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately. All identified asbestos will be fully abated by a licensed and regulated asbestos abatement contractor under a formal plan to be written, submitted and in accordance with the DEP.

IT IS THE RESPONSIBILITY OF ALL SUBCONTRACTOR FOREMEN TO REVIEW THE HAZOUDOS MATERIAL REPORT & CORRESPONDING ABATEMENT REPORT WITH THEIR WORKERS.  A copy of the hazardous Material/abatement report will be on site at all times and available to anyone who requests it.

All work and disposal will be done in compliance with state and federal regulations and standards.

Lead:  Lead is identified in the Woodward & Curran Report Dated 12/10/2020.   Workers who will need to perform work on painted surfaces may need to disturb lead in paint by drilling, sawing, demo, fastening, or carpentry. In doing so they will use saws, drills, screw guns, impact wrenches, sawzalls, hand wrenches, ads, crowbars, hammers, and other hand tools.  Consigli Construction does possess historical data to show that drilling, sawing, light demo, installation of hangers, hanging sheetrock, fastening, and carpentry do not put the employee above the action level. Despite this additional monitoring will be done. An exposure assessment will be done by all subcontractors for all task prior to when the full scale of this work is to take place. This does not mean that lead could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately.  All workers on this must have completed Lead Awareness training prior to starting on this project. Hand wash stations will be provided to ensure proper hygiene during the project.  An exposure assessment will also be done for any task which will disturb any lead containing material.

Silica:   Any activity which can produce silica dust will use engineering controls to keep dust to a minimum.  A written exposure plan must be developed for all silica producing tasks that clearly defines the following: 1) A description of the tasks in the workplace that involve exposure to respirable crystalline silica; 2) A description of the engineering controls, work practices, and respiratory protection used to limit employee exposure to respirable crystalline silica for each task; 3) A description of the housekeeping measures used to limit employee exposure to respirable crystalline silica; and 4) A description of the procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to respirable crystalline silica and their level of exposure, including exposures generated by other employers.

 There will be no dry cutting of any masonry material allowed; if water cannot be used then a dustless vacuum system consisting of HEPA dustless vacuum system will be used.  Prior to the project going full scale an exposure assessment of a worker grinding and cutting masonry while using the HEPA system an exposure assessment will be done so as to establish the silica exposure level.  No respirators will be issued without the express consent of the Consigli Safety department.  Nuisance mask like an N95 if used will be on a voluntary basis and at no time will these types of mask be issued to the workers.

Polychlorinated Biphenyl’s (PCBs):  PCB’s have been identified in the Woodward & Curran Report Dated 12/10/2020.  Areas have been identified according to their total PCB concentration (ppm).  Areas of regulated levels have been noted in the report. This does not mean that regulated levels of PCB’s could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately.

Light ballast unless labeled “No PCB’S” will be designated PCB containing, All PCB containing material shall be removed and disposed of in accordance with all local, state (MEMEP Special waste management rules 06-096-CMR 400) and federal regulations.  All other inquiries or locations in regards to PCB containing material can be located in the Hazardous Material survey. If identified on any of the materials to be impacted, PCBs will be abated. Any and all PCB remediation will be performed by a licensed /qualified contractor.

** Please review chapter 29 for additional details

Mold: Mold issues are not anticipated to be prevalent on this project, however if mold is discovered or water enters the construction space, the Consigli water infiltration and mold remediation policy will be implemented and followed.

** Please review chapter 22 for additional details

Noise:   All operations must be coordinated with the Consigli Superintendent to limit any excess noise impact on the surrounding areas. All activities and tasks which may cause loud noise will be monitored and neighbors will be notified of locations and dates/times of potential elevated noise levels.

** Please review chapter 29 for additional details

 Exposure to the Public, Staff, and Visitors: During all phases of construction pedestrian walkways around the project will be open and occupied. Some areas of project will be opened for construction at different times.  Any pedestrian walkway under any type of scaffold or overhead hazard will be provided with overhead protection. At no time is any worker allowed to enter any of the adjacent buildings. 

Fraternization between construction employees and project owners, staff, visitors will not be permitted.  Loud and profane language or clothing with offensive language will not be allowed on the jobsite. Extra efforts must be made to keep noise to a minimum.

Safety Spot Recognition Plan: The purpose of this plan is to instantly recognize workers “on the spot” for working safely and to reward those workers immediately. This will assist CCC reduce the complacency of workers on all of our projects. Members from the CCC and project teams (Supers, PM, APM, PE, OPM, Architect, Owners, etc..) will be provided with $5 Dunkin Donut gift cards (or similar) prior to their walk on site. They are to present these cards to workers who are working safely and or those taking additional steps to work safely.

After issuing the card, the name and hard hat sticker number of the worker as well as a brief description of what they were doing will be documented in a log that will be maintained in the field office. This shall be completed at a minimum of three times a week. It is required that different field staff take turns in issuing the cards to workers in the field. Also required will be the communication of who is be recognized to other sub-contractors/workers through foreman meetings and daily stand up meetings. At the end of the project the sub-contractor who has had the most workers recognized will receive an appropriate acknowledgment from CCC as well as some type of reward that is to be determined by CCC field staff.

Planning:  The project team will meet with the subcontractors prior to the commencement of their work scope and review the safety and logistics requirements of the project.  The project team shall be an integrated mix of owner, architect, engineer and Consigli Construction personnel.  If, after reviewing programs, Job Safety Analysis, and meeting with the affected individuals, the team is satisfied with the risk control direction, personnel will be permitted to begin work. 

COVID 19:   Please refer to separate Site Specific COVID 19 Plan developed for this project. 

Back End of Environmental Emergency Contact and Management Response