Evacuation Plan

Project #2767/#2768

NEU – Hastings Common Area & Hall Classrooms

320 Huntington Ave. Boston, MA

An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire).  Person/persons discovering emergency shall take the following actions:

  • Immediately dial 911
  • Consigli Superintendent: Owen Foley   (774)573-4621          

Evacuation order shall be signaled by:

  • Alerting all workers by the sounding of the building alarm. 
  • When the fire alarm sounds, you must promptly evacuate the building via the nearest safe exit route and head towards the assigned muster point location – Park on St Botolph St.
  • Critical operations shutdown procedures are not required, because no employees are authorized to delay evacuation for this purpose.
  • Portable fire extinguishers are provided if fire is in incipient/budding phase only.
  • Project Superintendent, and any other trained individual on site, is responsible for performing first aid on any injured person once outside evacuated area.
  • Project Superintendent, or a CCC designee, will be responsible for accounting for all CCC employees on site.
  • Project Superintendent, or the CCC designee, will be responsible for knowing what subcontractors are on site at all times.
  • A representative from each subcontractor will be responsible for accounting for their employees and notifying the CCC representative. For further assistance with emergency evacuation procedures, you may contact Safety Director Bryan Kingsbury at (508)808-9359.

Muster Point

Back End of Evacuation Plan and Muster Point