Site Specific Safety and Health Program

York County Judicial Center

511 Elm Street Biddeford, ME 04005

Consigli Project # 1765

 

 

Emergency Response Plan

ALL EMERGENCIES SHOULD BE REPORTED BY CALLING -9-1-1

SITE INFORMATION

This Emergency Response Plan (E.R.P.) is specifically developed for Consigli Construction work associated with this project.

SITE LOCATION

The construction site is located at 511 Elm Street Biddeford, ME 04005 The location for the project field office is currently at the Project jobsite (notifications of any changes will be provided).  When determined, the field office will become the Emergency Operations Center (EOC).

EMERGENCY TYPE

The following situations are considered emergency response actions and should be handled in accordance with the procedures outlined in this plan.

  • Serious Injury/Fatalities
  • Fire/Explosion
  • Structural Damage/Collapse
  • Weather or Geological Event
  • Environmental Incident
  • Traffic Disruption
  • Utility Damage
  • Illegal Activity
  • Labor Problems
  • Bomb Threats/Military Ordinance Unearthing
  • Acts of Terrorism

When reporting an emergency, please provide the following:

• Your location, phone number, and name;

• The location of the incident (building name, floor and room number);

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);

• The safest route to the incident.

Crisis Response Protocol:

  • Attend to the injured
  • Immediately contact Bryan Kingsbury (508)808-9359
  • Post person at front gate, only allow access to emergency responders
  • Record names/addresses of witnesses
  • Do not allow media on site
  • Refer all media inquiries to home office (See Consigli “Crisis Response Cards”)

A Consigli designated individual shall wait at the job site entrance to escort Emergency Services personnel as they arrive.

The following is a list of the Chain of Command/Call Hierarchy on the project for establishing lines of succession during communication involving all emergencies.

Back End of Emergency Response Plan

 

 

Emergency Contact Names and Numbers

1. First call: 911 Fire or police

2. CCC Superintendent: Spencer Seiferth (207)210-3531

3. CCC Superintendent:  Benjamin McAndrew (207)217-4782

4. CCC Project Manager: Parker LaMarre (774)217-9699

5. CCC PX: Chris Brown: (207)650-8663

6. CCC APM: Cassondra Sherman (207)232-8876

7. Corporate Safety: Bryan Kingsbury (508)808-9359

8. Safety Manager: Skip Boucher (207)217-7254

                                   Additional Contacts:

Biddeford Police Department: Non-Emergency (207)282-5127

Biddeford Fire Department: Non-Emergency (207)282-6632

Biddeford  DPW: (207)282-1579

CCC General Superintendent: Larry Chouinard (207)650-5204

CCC PE: Tyler Lewis (774)573-6790

CCC PE: Cassondra Sherman (207)232-8876

Owner Contact: Phil Johnston (207)615-4375                             

Back End of Emergency Contact Names and Numbers

 

 

Medical Facilities

Concentra Urgent Care 

85 Western Ave. South Portland, ME 04106

(207)774-7751

Southern Maine Healthcare 

1 Medical Center Dr, Biddeford, ME 04005

(207)283-7000

In case of emergency a Consigli representative will be dispatched to the Main entrance of the site to meet the responding Emergency Personnel and advise the individual in charge of the location of any chemicals or hazardous substances that may be present on any of the floors. SDS sheets will be readily available if needed by the Fire Dept.

In the event of a serious injury requiring the assistance of Biddeford EMS the injured worker will be kept as comfortable as possible.  Emergency first aid if necessary, will be administered.  Under no circumstances will the injured person be moved unless the worker’s life is in danger because of fire or calamity.  A worker will be assigned to meet the medical personnel at the above location to direct them to the location of incident.

In the event an evacuation is required all personnel at this job site will assemble at the designated Muster Point (see below). The Muster Point location may change due to phases of the project. The foreman for each company will meet at that location and take a head count of their staff and report to Consigli Superintendent. If for some reason a worker is unaccounted for, the fire department will be notified of the last location where the worker was observed.

 

Back End of Medical Facilities

 

 

Site Safety Plan

Scope of Proposed Operations: This project consists of the construction of a new court facility that will span four floors and 118,000 square feet.  The building will be constructed on a largely greenfield site a short distance from I-95.  This facility will house 11 court rooms, holding cells, clerks’ offices, judge/justice chambers, attorney spaces, administrative support spaces, jury & deliberation rooms, as well as support and public spaces. The building will utilize geothermal heating/cooling, a photo-voltaic rooftop array and a large mechanical penthouse on the roof level.  This project has a start date of Summer 2020 and has a substantial completion date of 12/2022

PURPOSE: The purpose of this Site-Specific Safety and Health Program is to illustrate Consigli’s approach to identifying project specific hazards and controls and how said risk is managed through a comprehensive Safety and Health Program.

S.A.F.E.: Staying Accident Free Every Day is the Safety Mission that forms the very foundation of the Consigli Safety Culture.  The S.A.F.E.  mission, which is supported by technology, (Predictive Solutions internal auditing instrument  which identifies and defines leading indicator related information); Leadership (Empowering our team members to assure safe projects); Humanization (Protect the ones you love by protecting yourself); Jobsite Gym (Morning warm-ups, stretch and flex); Training (Integrating sub-contractors into the Consigli Safety Culture); and Lean (nothing hit the ground), is the driving force behind Consigli’ s drive to our vision – ZERO.  ZERO is the philosophy that all accidents are preventable, and that no accident is acceptable.  The S.A.F.E. mission is the guiding force to achieving the Consigli Safety Vision which is ZERO.  

Identify the specific route in and out of the construction site (Traffic Management): All deliveries and waste removal shall be done using the pre-determined entrance communicated to contractors prior to start. All contractors will be responsible for adhering to City of Biddeford restrictions and regulations in regards to driving, parking and delivering materials. Pedestrians will be given the right of way at all times. Parking will not be designated.

Designated work hours (any work outside these hours must have prior CCC approval):  All work shall take place during business hours, Monday – Friday 7:00am to 3:30pm, any work which may need to take place outside of these hours will need to be approved by the CCC Superintendent.

Job Safety Analysis (JSA):  A JSA depending on level of hazard shall be conducted for each identifiable feature of work to be performed.  The JSA shall be submitted to Consigli superintendent/supervisor.  JSA shall be reviewed weekly, signed by all workers including their supervisor, with all involved personnel performing that particular task.

Post Incident Review: Any incident that results in a recordable injury will require a post incident review. The worker who was injured along with their foreman/Safety Personnel/PM/Sup/etc… will need to fill out Appendix N (post incident review form) and attend this meeting. At this meeting they will re-emphasize their commitment to safety, determine chronology of events, identify contributing factors, identify root cause, provide improvement plan to prevent reoccurrence and discuss disciplinary actions taken (if any). Findings from this meeting will be shared/disseminated with all contractors on site to prevent reoccurrence.

Excavations: Required permitting will be obtained before any excavating is to begin.  If necessary, tabulated data/engineering for shoring and shielding systems will be obtained and available on site at all times when in use. All excavations will be inspected by a competent person on a daily basis.  Written excavation inspections will be done if the excavation exceeds 5’. 

  • Dig Safe Notification/utility locator – number/report will be posted in office if needed.

  • Copies of soil engineering and tabulated data sheets for all trench boxes or other    shoring/shielding systems brought on site will be provided to CCC and be kept in construction office.

**Review Chapter 19 for more detail

Fall Protection: All workers exposed to a fall of 6′ or greater shall be protected by guardrails safety nets or personnel fall arrest systems.  Fall protection required activities shall include, but are not limited to, steel erection (roof steel dunnage), leading edge work, roof framing, roofing installation, and exterior finishes.  Holes greater than 2” will be covered with acceptable material (3/4 plywood ½ steel) which will be secured and marked hole and capable of supporting 2x the intended load (cover must be able to withstand 2x times the intended axle load). 

Covers will stay in place until the hole/penetration has been filled with duct or Pipe riser which extends above the deck. Building perimeters and mezzanine leading edges shall be protected with cable guard rail system with turnbuckles to be installed for all straight runs and any straight run.                               

Before any work is to begin on the roof, it must be determined what method of fall protection will be implemented.  All workers working on a roof with a slope greater than 4 to 1 and exposed to a fall greater than 6 feet will have fall protection 100%of the time spent in this location.  Workers on a roof with a slope less than 4 to 1 may put flagging (six feet for roofers-15 feet for everyone else) lines up, whenever roofers and any other trade are on the same roof then the flagging must be pulled back to the maximum distance. All material will need to be kept a minimum of 6’ from the roof edge, any materials that may be blown off of the roof shall be secured/weighted down. 

The use of Safety Monitors is not permitted!!!              

**Review Chapter 13 for more detail

Steel Erection: Steel workers will be required to use fall protection at 6′. Consigli will release documentation when column footings reach 75% of breaking strength.  The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations. Decks will only be turned over for general use after they have undergone an inspection by a member of the CCC safety department. 

The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations.  Fall protection will be determined for connectors after pre-construction meeting with sub is held.  Fall protection will be required at 6’, at all times during steel erection

Once decking is complete and all required fall protection is installed, CCC will walk the area with the steel erection subcontractor.  Provided all required elements of fall protection are in place, CCC will complete and give a copy of the “custody of fall protection” form to the steel erection subcontractor.  Maintenance and overall responsibility of the fall protection system will fall to CCC.

Work on Ladders: All work on step ladders/straight ladders will be done correctly per manufacturer’s recommendations.  Any worker who is on a step/straight ladder and could be exposed to a fall greater than the height of their work on the ladder will be required to install a form of fall protection.  Step ladders will not be used as a form of access to a walking /working level, also all straight ladders will be tied of when installed for use.  Only ladders with a rating Type 1A or 1AA will be allowed on Consigli projects.

Scaffold and elevated work platforms:  All scaffolds; supported frame, pipe staging and aerial lift and scissor lift platforms will be inspected daily before each shift by a competent person designated by each individual contractor who will be using it, which will be documented on Inspection tags located at the stair tower/access to each section. A scaffold checklist guide will be provided by CCC to each sub-contractors designated persons upon request to aid them with their daily inspection. All sub-contractors will be required to complete a written scaffold inspection once their scaffold is completed. After the initial written inspection, they will be responsible for inspecting and signing an inspection tag on a daily. All contractors who will be erect scaffold will provide CCC with certification/Qualification of scaffold erection training as well as an erection/dismantling plan. Fall protection is required 100% during erection/dismantling. Overhead protection will be provided for all access points at any buildings which are located under any form of scaffolding.

Fall protection is required at 6’ on all scaffolds, on mobil scaffold fall protection is required at 4’. Mobil staging with a work platform with a height to base ratio greater than two to one will require outriggers. All scaffolding that is procured by CCC and is over 15’ in height will require that the CCC Safety Department review the scaffold prior to it being turned over for use by tradesmen. 

** Please review chapter 14 for additional details.  

Aerial/Scissor Lifts:  If aerial/scissor lifts are required the area and ground conditions, in the intended work area, will be inspected for overhead power lines, sink holes, covers, or any other unsafe conditions which cause an unsafe incident.  Aerial lift platforms will be inspected daily before each shift by a competent person designated.  All who will be performing work from an aerial lift will show documented proof of training prior to using the lift.  Steel plates or equipment mats will be placed on the ground above any utility/ underground structures if there will be Aerial lifts operating directly over them. Workers will be tied off at all times when using an aerial lift.


HazCom/Global Harmonization:
  All Materials and chemicals used on-site will have Safety Data Sheets (SDS) provided before being brought onsite.

  • SDS sheets on file in Consigli Construction’s Site Safety Plan
  • All SDS sheets shall be readily accessible.

** Please review chapter 20 for additional details.  

Fire Protection: During construction, a Hot Work Permit is required for any activity that generates heat, sparks or has an open flame. This will be coordinated through Consigli as well as Boston Fire Department. (as required).  All workers involved in hot work activities shall be trained as required. Any hot work will stop one hour before the regular end of the day work stoppage.   Flammables will not be stored inside the building or left overnight on the scaffold or in the building.  All combustible or flammable materials will be stored in an appropriately rated lockable cabinet located no closer than 50 feet from the nearest structure.

Fire extinguishers will be provided for every 3000 square feet.  They will be installed on job made stands and conspicuously located throughout.  They will be part of the daily inspection with extinguisher log completed monthly.  Storage of any acetylene cylinders will be done in a secure and upright area, with good ventilation.  This will be a strict no smoking project. All penetrations leading outside of the construction area will be fire stopped using approved fire rated material prior to the end of each shift.

**Review Chapter 17 for more detail.

Electrical: All electrical tools, cords and equipment must be in good working order. To that end, all electrical tools and components must be visually checked on a daily basis.  Any tools with damaged cords or damaged cords must be taken out service… All cords must be equipped with a ground pin, flat three wire cords are not allowed.  SJO and SJT or other similarly rated cords only shall be used.  The electrician will be responsible for all temp power and any temp lighting that may be needed.  They will coordinate all lock out tag out procedures. All temporary power for the project will be installed on protected and dedicated circuits with 100% GFCI protection.  GFCI will be tested by the electric contractor weekly to assure proper function with a log book filed with CCC monthly.  No live electrical work will be conducted.  No live electrical work will be conducted per NFPA 70E.

**Review Chapter 26 for more detail

Exposure to Street Traffic:  All deliveries will be made at a designated location unless otherwise directed by Superintendent.  There will be exposure to live vehicular traffic and flaggers will be used when required. All speed limits will be obeyed, and deliveries will be made as to not coincide with buildings scheduled deliveries. All traffic control signage (if needed) will meet City of Portland requirements before being installed.  Coordination with them as well as its police will be required when any equipment will be set up/used in the street/parking lot. Fire department access will be maintained and kept open for emergency responders.

Utility Exposures:  Any overhead power lines will be located and identified prior to use of any equipment which may come in to contact with them. All sidewalks will be protected if equipment is to be driven over them.

Steel Erection: Steel workers will be required to use fall protection at 6′. Consigli will release documentation when column footings reach 75% of breaking strength.  The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations. Decks will only be turned over for general use after they have undergone an inspection by a member of the CCC safety department.

The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations.  Fall protection will be determined for connectors after pre-construction meeting with sub is held.  Fall protection will be required at 6’, at all times during steel erection

Once decking is complete and all required fall protection is installed, CCC will walk the area with the steel erection subcontractor.  Provided all required elements of fall protection are in place, CCC will complete and give a copy of the “custody of fall protection” form to the steel erection subcontractor.  Maintenance and overall responsibility of the fall protection system will fall to CCC.

** Please review chapter 16 & Attachment H for additional details

Crane: FAA Permit may be required for some heights of cranes.  Contractor providing crane shall perform FAA permit to determine if needed.  All cranes will require independent annual 3rd party inspections.  Crane work will be permitted for operation only after detailed lift plans are submitted and reviewed by Consigli.   It is anticipated that these cranes will be hydraulic.  In the event that a lattice boom crane is utilized, then the crane must get an on-site 3rd party inspection once the crane is assembled, prior to operation.

 There is a requirement to assure that certified riggers, signalmen, and crane assemblymen are utilized.  All picks are to be done by a licensed operator.  As previously mentioned, a detailed pick plan will be required to assure that no picks are critical in nature.  Critical picks are defined as those involving 2 cranes lifting simultaneously, a pick that is over 75% of capacity, a pick that involves the lifting of a man basket, or any other lift that is deemed to involve special conditions.  Location and set up will be reviewed with crane operator prior to set up and pick.  All lifting operations will require that the operator and any involved contractors follow the steps listed below as well as in CCC Crane Safety policy.

 1. All Hoisting equipment will have an up to date 3rd party inspection certificate with the equipment which will be copied and filed in the office trailer.

2. All lattice boom cranes will have an independent 3rd party inspection completed each time one is set up on the project, after assembly and prior to operation.

3. All equipment operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the State of MA.  All crane operators must be qualified by their employer and documentation of the employer qualification included in the lift plan.

4. All underground vaults and existing utilities will be marked before as well as before any crane is set up.

5. Documented rigging equipment inspections.

6. Documented daily crane inspections filed with CCC weekly.

7. Documented rigger and hand signalman training will be provided.

** Please review chapter 24 for additional details.  

Equipment issues:   All operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the state of ME.  All safety devices and warning alarms must be in good working order and all leaks are to be repaired immediately.  All equipment will be used in accordance with the manufacturer’s recommendations for safe usage and have its operator’s manual as well as an extinguisher with it at all times.  Subcontractors who will have equipment on site will be responsible for having a spill kit available at all times.

** Please review chapter 24 for additional details

Confined Space:  A written plan will be needed to work in any tanks/vaults and crawl spaces during this project which have been designated permit confined spaces by CCC, this plan must include air monitoring.

** Please review chapter 21 for additional details.  

Designated First Aid Plan:   All injuries no matter how minor must be reported to Consigli Superintendent immediately. The superintendent will then report all injuries to the CCC Safety Director.  A fully stocked first aid kit and blood borne pathogens kit shall be maintained on the project site.  Only properly trained personnel will administer first aid.  Consigli Construction shall follow Site Safety Plan for first Aid.  Report any incidents to the Safety Director

** Please review chapter 1 and 27 for additional details.  

Substance Abuse: As a condition of employment, all Consigli personnel are required to submit to a urinalysis test for determination of the presence of illegal substances.  A positive result will disqualify the applicant for employment on this project.

Evacuation Plan (RACE, and Routes of Egress): Please refer to the Evacuation Plans attached.  All Consigli employees shall attend the Project Safety Orientation.  Consigli Construction’s Job Supervisor will conduct a safety orientation talk to each employee and subcontractor to site specific fire safety protocols.

Emergency Management Response: In the event of an Emergency the construction workers shall leave all 3 of the building immediately. Point of assembly/muster shall be located next to the field office trailers.  In the Event of a DISASTER, the Superintendent or Safety director shall instruct the construction workers to leave the site or remain in place and await further instruction.  The following steps should be taken in the event of an emergency

When reporting an emergency, please provide the following:

• Your location 511 Elm Street Biddeford, ME 04005 phone number, and name;

• The location of the incident (building name, floor and room number);

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);

• The name and amount of the material spilled (if applicable); and

• The safest route to the spill (if applicable).

** Please review chapter 8 for additional details.  

Minimum Site Safety Requirement:  All Consigli workers, and any subcontractors, shall have, at a minimum, an OSHA 10 Hour Construction Safety Outreach training certificate and shall provide documentation of training.

 Personnel Protective Equipment (PPE):  All CCC and sub-contractor workers will wear hard hats and safety glasses at all times.  All CCC personnel performing work with their hands shall be required to wear gloves that are appropriate to the task.  When not performing actual work with their hands workers will be required to have them available for immediate use. Face shields will be required for all personnel who are performing overhead work, using metal chop saw or any type of metal grinding.  All welders will be required to have hard hats with integral welding shields.

Materials Management: Materials management, getting materials into and out of the project, will be done through site entrance gates and loading dock. Getting materials into and out of the project will be a challenge that needs to be adequately planned.  All deliveries are to be scheduled with the CCC Superintendent.  A comprehensive Job Safety Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed in a reasonable amount of time will be delivered to the site. Attention must be paid to structural analysis in regards to loading floors with material and equipment

Lean requirements/Materials Management/House Keeping: Getting materials into and out of the project will be a challenge that needs to be adequately planned.  All deliveries are to be scheduled with the CCC Superintendent.  A comprehensive Job Safety Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed within three days’ time will be delivered to the site. Attention must be paid to structural analysis in regards to loading existing floors with material and equipment. Listed below are additional Lean requirements

  • No materials shall be delivered to the site earlier than 3 days before said materials are to be installed/put into place.  If materials have to be delivered before that 3 day time period, subcontractor shall get prior approval from Consigli Superintendent.  Because of this, notification / scheduling is required for all deliveries to the site. Subcontractors must notify Contractor at least 24 hours in advance. Contractor has the right to refuse any deliveries not properly scheduled or due to logistical constraints as necessary.

  • All subcontractors’ delivered materials shall be placed on wheeled carts, wheeled racks or in wheeled bins so as to necessitate easy relocation in the event materials need to be moved.  Carts, racks, or dolly’s shall not exceed manufacturers intended weight loads.  Materials/tools can be delivered and stored on pallets only if pallet jacks are delivered simultaneously with said delivery to provide for ready mobility.  Additionally, pallet jacks need to remain in immediate area.    Each subcontractor will need to supply their own pallet jacks for their own materials and keep their pallet jack within reasonable distance at all times.

  • All work stations shall be provided with wheeled trash bins for immediate placement of all debris produced as a part of the subcontractors operations.  All trash will be immediately placed in wheeled containers provided by Consigli.

  • All subcontractors shall use rubber wheeled carts when moving material or removing trash from a building.  Any damage caused by the Subcontractor shall be repaired at the cost of the Subcontractor.  Back charges will be appropriately assessed for the cost of the repairs.  No trash or materials shall be left on the floor. 

  • Subcontractors shall, where feasible, elevate all electrical extension cords, hoses, or cables – removing them from all walking/working surfaces.  Electrical Cords, when elevated shall be supported or suspended in a manner that does not subject them to damage. 

  • Storage of delivered materials in cardboard containers shall be discouraged.  When materials must stay in cardboard containers, said containers shall be removed from the projects immediately after product is unpacked. 

  • Subcontractor will participate in schedule development meetings as required by Consigli.

Back End of Site Safety Plan

 

 

Environmental Emergency Contact and Management Response

Consigli identified Emergency Response Subcontractor;

Name: Cynn Environmental Services, Inc. (781)341-1777

100 Tosca Drive Stoughton, MA 02072

Silica:   Any activity which can produce silica dust will use engineering controls to keep dust to a minimum.  A written exposure plan must be developed for all silica producing tasks that clearly defines the following: 1) A description of the tasks in the workplace that involve exposure to respirable crystalline silica; 2) A description of the engineering controls, work practices, and respiratory protection used to limit employee exposure to respirable crystalline silica for each task; 3) A description of the housekeeping measures used to limit employee exposure to respirable crystalline silica; and 4) A description of the procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to respirable crystalline silica and their level of exposure, including exposures generated by other employers.

 There will be no dry cutting of any masonry material allowed; if water cannot be used then a dustless vacuum system consisting of HEPA dustless vacuum system will be used.  Prior to the project going full scale an exposure assessment of a worker grinding and cutting masonry while using the HEPA system an exposure assessment will be done so as to establish the silica exposure level.  No respirators will be issued without the express consent of the Consigli Safety department.  Nuisance mask like an N95 if used will be on a voluntary basis and at no time will these types of mask be issued to the workers.

Mold: Mold issues are not anticipated to be prevalent on this project, however if mold is discovered Consigli’s mold remediation policy will be implemented and followed.

** Please review chapter 22 for additional details

Noise: Noise exposure will be a concern so all operations must be coordinated with the Consigli Superintendent to limit any excess noise impact on the surrounding areas. All activity r task which may cause load noise will be restricted as needed so as to limit the impact on neighbors.

** Please review chapter 29 for additional details

Exposure to the Visitors, Staff: During all phases of construction pedestrian walkways around the project will be open and occupied. Any pedestrian walkway under any type of scaffold or overhead hazard will be provided with overhead protection. At no time is any worker allowed to enter any of the adjacent buildings.  Non fraternization with staff  and guests will be stressed with all subcontractor personnel during orientations. 

Additional Controls: Prior to start of any work, all personnel involved in the project, including project managers must be:

  1. Trained and orientated by Consigli Construction.  Stickers will be issued and displayed on hard hat.
  2. All individuals working on this project will go through a comprehensive Safety Orientation which will cover all company safety rules regulations and procedures as well as communicating St. Elizabeth’s Medical Center specific requirements. 

Safety Spot Recognition Plan: The purpose of this plan is to instantly recognize workers “on the spot” for working safely and to reward those workers immediately. This will assist CCC reduce the complacency of workers on all of our projects. Members from the CCC and project teams (Supers, PM, APM, PE, OPM, Architect, Owners, etc..) will be provided with $5 Dunkin Donut gift cards (or similar) prior to their walk on site. They are to present these cards to workers who are working safely and or those taking additional steps to work safely.

After issuing the card, the name and hard hat sticker number of the worker as well as a brief description of what they were doing will be documented in a log that will be maintained in the field office. This shall be completed at a minimum of three times a week. It is required that different field staff take turns in issuing the cards to workers in the field. Also required will be the communication of who is be recognized to other sub-contractors/workers through foreman meetings and daily stand up meetings. At the end of the project the sub-contractor who has had the most workers recognized will receive an appropriate acknowledgment from CCC as well as some type of reward that is to be determined by CCC field staff.

Planning:  The project team will meet with the staff before the project start to review any site specific safety and health requirements. The project team shall be an integrated mix of owner, architect, engineer and Consigli Construction personnel.  If, after reviewing programs and meeting with the individuals, the team is satisfied with the risk control direction, personnel will be permitted to begin work. 

Working Safely With COVID 19

  • Employees experiencing any symptoms (runny nose, headache, cough, sore throat and/or fever) shall stay home and contact your Supervisor.  Supervisors should immediately communicate any individuals reporting symptoms to the Consigli Superintendent.
  • Any employee that has had contact with someone that has a presumed positive for COVID-19 or someone awaiting testing COVID-19 should stay home and contact their supervisor.  Supervisors should immediately communicate any individuals reporting potential contact to the Consigli Superintendent.
  • Any individuals that have traveled outside of the United States should stay home and contact their supervisor.  Supervisors should immediately communicate individuals reporting foreign travel to the Consigli Superintendent to discuss authorization to work on site. 

** This Screening Protocol will be, maintaining proper 6’ spacing, with everyone on site at the start of every shift. **

The following GUIDELINES need to be followed

  • Consigli Project Team shall communicate with our customer to confirm we are in compliance with all facility work rules.
  • All subcontractor’s Project Managers, Assistant PM’s, Safety Officers, etc. should work remotely. 
  • Any site visits by non-essential personnel should be discussed with the Consigli project team.
  • All meetings will be done via Skype or conference calls. 
  • All vendors and delivery drivers are prohibited from entering the site.  When deliveries arrive near the site, contact the Consigli Superintendent for direction. 
  • Avoid cafeterias and high activity areas.
    • When possible eat outside or in isolated area.
    • As much as possible avoid intermingling with other crews or groups
    • Prohibit all food and drink inside the work areas
    • Any lunch rooms within the work areas should be closed
  • Wash or sanitize hands frequently
    • Always before and after any lunch period or break time
  • Maintain social distancing when practical
    • Preferably maintain at least 6’ between yourself and others
    • If working with a partner is required assure proper hygiene practices are followed
  • Disinfect frequently touched objects and surfaces, such as tools, keyboards, light switches and tables at least twice per day. Most household cleaners, such as bleach wipes or alcohol, will kill the virus.
  • Utilize proper etiquette when coughing or sneezing
  • Discontinue the use of community water, coffee, or food

** This screening protocol will be completed, maintaining proper 6’ spacing, with everyone on site at the start of every shift. 

Back End of Environmental Emergency Contact and Management Response