Evacuation and Muster Plan
Hobson’s Landing Project #1882 An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire). Person/persons discovering emergency shall take the following actions:- Immediately dial 911 The address for the project is 383 Commercial St, Portland Maine, 04101
- Contact Consigli Superintendent: Mark Carpentier (774)217-2233
- Alerting all workers by the sounding of three long blasts of an air horn or building alarm.
- Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
- Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
- Portable fire extinguishers are provided if fire is in incipient/budding phase only.
- Superintendent, Mark Carpentier, and any other trained individual on site, is responsible for performing first aid on any injured person once outside evacuated area.
- After an emergency evacuation, employees are directed to gather next to the field office building located on the South elevation of the site.
- Superintendent Mark Carpentier, or a CCC designee, will be responsible for accounting for all CCC employees on site.
- Superintendent Mark Carpentier, or the CCC designee, will be responsible for knowing which subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Carpentier or the CCC representative.
- For further assistance with emergency evacuation procedures, you may contact Safety Director Dan Della-Giustina at (508)686-6008.
Muster Point
Back– End of Evacuation and Muster Plan