Site Specific Safety and Health Program
Hobson’s Landing
383 Commercial St. Portland, ME 04101
Project # 1882
Emergency Response Plan
Hobson’s Landing – Project #1882
SITE INFORMATION
This Emergency Response Plan (E.R.P.) is specifically developed for Consigli Construction work associated with at the old Rufus Deering Lumber to the new Hobson’s Landing project(s).
SITE LOCATION
The construction site is located on at the Rufus Deering Lumber property Portland, ME. The address for project is 383 Commercial St. Portland, ME 04101. The location for the project field office is currently located on the second floor of the retail store. (notifications of any changes will be provided). When determined, the field office will become the Emergency Operations Center (EOC).
EMERGENCY TYPE
The following situations are considered emergency response actions and should be handled in accordance with the procedures outlined in this plan.
- Serious Injury/Fatalities
- Fire/Explosion
- Structural Damage/Collapse
- Weather or Geological Event
- Environmental Incident
- Traffic disruption
- Utility Damage
- Illegal Activity
- Labor Problems
- Bomb Threats/Military Ordinance Unearthing
- Acts of Terrorism
The following is a list of the Chain of Command/Call Hierarchy on the project for establishing lines of succession during communication involving all emergencies.
Back– End of Emergency Response Plan
Emergency Contact Names and Numbers
1. First call: 911.
2. CCC Superintendent: Michael Carpentier – (774)217-2233
3. Project Manager: Travis Parker – (774)278-4721
4. Project Engineer: Austin Moore – (207)233-1778
5. Dan Della-Giustina: Corporate Safety – (508)686-6008
6. Senior Project Manager: Bert Kiesow – (207)615-1523
7. Project Executive: Thomas Weeks – (207)232-6416
Additional Consigli Construction Contacts:
- CCC Safety Manager: Eddy Pellerin – (508)962-3974
- Consigli Construction, Inc. – Portland Office – (207)773-2800
Local Emergency Services.
Portland Police General Info. – (207)874-8300
ME State Police (non-emergency) – (207)624-7076
Portland Fire Department (non-emergency) – (207)874-8400
Portland Water Emergency – (207)761-8300
Non Emergency – (207)774-5961
Portland Sewer / Public Works – (207)874-8462
Central Maine Power 1-(800)696-1000
Dig Safe 811
Dig Smart – (207)749-7231
Unitil Emergency 1-(866)900-4460
Non Emergency 1-(866)933-3821
Client Environmental Services
Abatement Professionals – (207)773-1276
Back– End of Emergency Contact Names and Numbers
Medical Facilities
Concentra
85 Western Avenue South Portland, ME 04106
Phone: 207-774-7751
Directions to Concentra
1. Start out going south on Commercial St/US-1 Alt S toward Wrights Wharf.
Continue to follow US-1 Alt S.
Then 1.50 miles 1.50 total miles
2. Stay straight to go onto Veterans Memorial Bridge.
Then 0.76 miles 2.26 total miles
3. Merge onto I-295 S toward S Portland/Scarborough.
Then 0.82 miles 3.07 total miles
4. Take the WESTBROOK ST exit, EXIT 3, toward JETPORT/KAPLAN UNIVERSITY/HUSSON
UNIVERSITY.
Then 0.29 miles 3.36 total miles
5. Merge onto ME-9.
Then 0.34 miles 3.70 total miles
6. 85 Western Ave, South Portland, ME 04106-2411, 85 WESTERN AVE.
Maine Medical Hospital
22 Bramhall St. Portland, ME 04102
Phone: 207-662-0111
Directions to Maine Med Hospital
1. Start out going southwest on Commercial St/US-1 Alt S toward Wrights Wharf.
Then 0.06 miles 0.06 total miles
2. Take the 1st right onto High St.
High St is just past Hobsons Wharf
Becky’s is on the left
If you reach Holyoke Wharf you’ve gone a little too far
Then 0.37 miles 0.42 total miles
3. Turn left onto Congress St/ME-26.
Congress St is just past Spring St
If you reach Deering St you’ve gone a little too far
Then 0.51 miles 0.93 total miles
4. Turn left onto Bramhall St.
Bramhall St is just past Mac Millan Rd
If you reach Ellsworth St you’ve gone a little too far
Then 0.18 miles 1.11 total miles
5. 22 Bramhall St, Portland, ME 04102-3134, 22 BRAMHALL ST is on the right.
Emergency Procedures: A Consigli representative will be dispatched to the Main entrance of the site to meet the responding Emergency Personnel and advise the individual in charge of the location of the incident as well as any chemicals or hazardous substances that may be present on any of the floors. Safety Data Sheets will be readily available if needed by the Fire Dept.
In the event of a serious injury requiring the assistance of Portland EMS the injured worker will be kept as comfortable as possible. Emergency first aid if necessary will be administered. Under no circumstances will the injured person be moved unless the worker’s life is in danger because of fire or calamity. A worker will be assigned to meet the medical personnel at the above location to direct them to the location of incident.
In the event an evacuation is required all personnel at this job site will follow the building/site evacuation plan and meet at the designated Muster Point (see below). The foreman for each company will meet at that location and take a head count of their staff and report to Consigli Superintendent. If for some reason a worker is unaccounted for, the fire department will be notified of the last location where the worker was observed.
Back– End of Medical Facilities
Site Safety Plan
I. Scope of Proposed Operations: The project will begin November 2018 and will end in August 2020. The Project will consist of the demolition and removal of all material and wood storage buildings onsite with exception of the Rufus Deering Office Building which will house the Consigli Field Office. Site improvements will be made to the onsite soils, drainage, and temporary added support and protection of the original sea wall. Building construction will consist of a steel support structure with concrete slabs on deck. The building’s exterior façade will be comprised of structural light gage metal framing with a glass board sheathing and combination of fiber cement panels and brick veneer. The building will be 7 stories in total housing 1 level of commercial retail space, 2 levels of parking, and 6 total stories of residential condominiums.
S.A.F.E.: Staying Accident Free Every Day is the Safety Mission that forms the very foundation of the Consigli Safety Culture. The S.A.F.E. mission, which is supported by technology, (Predictive Solutions internal auditing instrument which identifies and defines leading indicator related information); Leadership (Empowering our team members to assure safe projects); Humanization (Protect the ones you love by protecting yourself); Jobsite Gym (Morning warm-up stretch program); Training (Integrating sub-contractors into the Consigli Safety Culture); and Lean (nothing hit the ground), is the driving force behind Consigli’ s drive to our vision – ZERO. ZERO is the philosophy that all accidents are preventable, and that no accident is acceptable. The S.A.F.E. mission is the guiding force to achieving the Consigli Safety Vision which is ZERO.
Identify the specific route in and out of the construction site (Traffic Management): Main construction access will be restricted to routes pre-determined by Consigli. All contractors will be responsible for adhering to Portland restrictions and regulations regarding driving, parking and delivering materials. Pedestrians will be given the right of way at all times. Parking will be not be designated for construction workers and all crews must make their own offstreet parking arrangements. This will be reviewed during orientation.
Designated work hours (any work outside these hours must have prior CCC approval): All work shall take place during business hours, Monday – Friday 7:00am to 3:30pm, any work which may need to take place outside of these hours will need to be approved by the CCC Superintendent.
Activity Hazard Analysis (AHA): An AHA/JHA depending on level of hazard shall be conducted for each identifiable feature of work to be performed. The AHA/JHA shall be submitted to Consigli superintendent/supervisor. AHA/JHA shall be reviewed weekly, signed by all workers including their supervisor, with all involved personnel performing that particular task.
Demolition: Prior to the start of demo operations, the contractor preforming demo will confirm that all utilities leading into the area have been made safe. The electrician will disconnect and lock out all electrical, the plumber will do the same with any plumbing lines, and the HVAC subcontractor will do the same on the HVAC piping and duct work. Lock out tag out will be reviewed during the pre-construction safety meetings to assure disconnect and responsibility for protection of existing utilities is safe for any construction activities to commence. In spaces where some electrical or mechanical must remain live, a color coding system will be utilized for easy identification of live utilities that must stay active and utilities that must be removed. Any and all utilities spray painted Red are not to be touched and need to be protected during all operations. Utilities spray painted Green are to be removed as part of the selective demolition process only after lock-out/tag-out has been confirmed and utilities tested. If any utilities are unmarked, they shall be considered live. The demo contractor will be responsible for completing CCC demo checklist prior to the start of any work in their target areas
Fall Protection: Project fall exposures, all work over 6 feet requires some form of fall protection in accordance with CCC fall protection policy. All fall protection for work preformed on Scaffold will be needed at a height of 6 feet or greater. All scaffold erectors will maintain the ability to have fall protection by donning a harness and lanyard at all times during erection. Holes greater than 2” will be covered with acceptable material (3/4 plywood ½ steel) which will be secured and marked hole (cover must be able to withstand four times the intended load). Covers will stay in place until the hole/penetration has been filled. Building perimeters (to be protected with cable guard rail system with turnbuckles to be installed for all straight runsand any straight run over 100 feet. Before any work is to begin on the roof it must be determined what method of fall protection will be implemented (fall protection plan, 100% tie off, guard rails, flagging etc.) All workers working on a roof with a slope greater than 4 to 1 and exposed to a fall greater than 6 feet will be tied off 100% of the time spent in this location. Workers on a roof with a slope less than 4 to 1 may put flagging (six feet for roofers-15 feet for everyone else) lines up, whenever roofers and any other trade are on the same roof then the flagging must be pulled back to the maximum distance. Holes greater than 2” will be covered withacceptable material (3/4 plywood ½ steel) which will be secured and marked hole (cover must be able to withstand 2x the intended axle load). Covers will stay in place until the hole/penetration has been filled with duct or Pipe riser which extends above the deck. The use of safety Monitors is prohibited.
Roof Work: Before any work is to begin on the roof it must be determined what sections of the roof will be worked a method of fall protection will be implemented (100% tie off, guard rails, flagging etc. the use of safety monitors is not allowed) Holes greater than 2” will be covered with acceptable material (3/4 plywood ½ steel) which will be secured and marked hole (cover must be able to withstand four times the intended load). Covers will stay in place until the hole/penetration has been filled with duct or Pipe riser which extends above the deck. The roof will be made water tight by the end of each shift. The use of safety Monitors is prohibited.
**Review Chapter 13 for more detail
Work on Ladders: All work on step ladders/straight ladders will be done correctly per manufacturer’s recommendations. Any worker who is on a step/straight ladder and could be exposed to a fall greater than the height of their work on the ladder will be required to install a form of fall protection. Step ladders will not be used as a form of access to a walking working level, also all straight ladders will be tied of when installed for use. Only ladders with a rating Type 1A or 1AA will be allowed on Consigli projects.
Scaffold and elevated work platforms: Mobile scaffold (baker staging), system scaffold and mast climber scaffold use is expected. All scaffolds supported frame, pipe staging and lift platforms will be inspected daily before each shift by a competent person designated by each individual contractor who will be using it, which will be documented on Inspection tags located at the stair tower to each section… A scaffold checklist will be provided by CCC to each sub contractors designated persons to aid them with their daily inspection. All contractors who will be erect scaffold will provide CCC with certification/Qualification of scaffold erection training as well as an erection/dismantling plan. Fall protection is required 100% during erection/dismantling. Overhead protection will be provided for all access points at any buildings which are located under any form of scaffolding. Fall protection is required at 6’ on all scaffolds, on mobil scaffold fall protection is required at 4’. Mobile staging with a work platform with a height to base ratio greater than two to one will require outriggers.
** Please review chapter 14&15 for additional details.
Aerial/Scissor Lifts: If lifts are required, the area, ground conditions, and slab strength, in the intended work zone, will be inspected for overhead power lines, sink holes, covers, or any other unsafe conditions which cause an unsafe incident. Aerial lift platforms will be inspected daily before each shift by a competent person designated by the affected employer. All who will be performing work from an aerial lift will show documented proof of training prior to using the lift. Steel plates or equipment mats will be placed on the ground above any utility if there will be Aerial lifts operating on them. Workers will be tied off at all times when using an aerial lift.
Chemical and Materials/Global Harmonization: All Materials and chemicals used on-site will have Safety Data Sheets (SDS) provided before being brought onsite.
- SDS sheets on file in Consigli Construction’s Site Safety Plan
- All SDS sheets shall be readily accessible.
** Please review chapter 20 for additional details.
Fire Protection: The hot work permit program will be implemented for all hot work to be conducted on the project on a daily basis. This will be coordinated through the school as well as Fire Department (if needed). All hot work will stop one hour before the regular end of the day work stoppage. 20lb extinguishers of ABC rating will be positioned accordingly through the project. Flammables will not be stored inside the building or left overnight on the scaffold or in the building. All combustible or flammable materials will be stored in an appropriately rated lockable cabinet located no closer than 50 feet from the nearest structure. Fire extinguishers will be provided for every 3000 square feet. They will be installed on job made stands and conspicuously located throughout. They will be part of the daily inspection with extinguisher log completed monthly. Storage of any acetylene cylinders will be done in a secure and upright area, with good ventilation. This will be a strict no smoking project. All penetrations leading outside of the construction area will be fire stopped using approved fire rated material prior to the end of each shift.
**Review Chapter 17 for more detail.
Electrical: All electrical tools, cords and equipment must be in good working order. To that end, all electrical tools and components must be visually checked on a daily basis. Any tools with damaged cords or damaged cords must be taken out service… All cords must be equipped with a ground pin, flat three wire cords are not allowed. SJO and SJT or other similarly rated cords only shall be used. The electrician will be responsible for all temp power and any temp lighting that may be needed. They will coordinate all lock out tag out procedures. All temporary power for the project will be installed on protected and dedicated circuits with 100% GFCI protection. GFCI will be tested by the electric contractor weekly to assure proper function with a log book filed with CCC monthly. No live electrical work will be conducted.
**Review Chapter 26 for more detail
Cranes: Location and set up will be reviewed with crane operator prior to set up and pick. All lifting operations will require that the operator and any involved contractors follow the steps listed below as well as in CCC Crane Safety policy
1. All Hoisting equipment will have an up to date 3rd party inspection certificate with the equipment which will be copied and filed in the office trailer.
2. All lattice boom cranes will have an independent 3rd party inspection completed each time one is set up on the project.
3. All workers working with the crane shall have all appropriate signalmen/rigging qualifications.
3. All equipment operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the State of Maine.
4. NCCO certification will be required for all crane operators who will be operated on site for 5 or more continuous days.
5. All underground vaults and existing utilities will be marked before any excavation can begin as well as before any crane is set up.
6. Cribbing for outriggers shall be at minimum 3X the area width of outrigger floater. (Cranes only)
** Please review chapter 24 for additional details.
Confined Space: A written plan will be needed to work in any tanks/vaults and crawl spaces during this project which have been designated permit confined spaces by CCC, this plan must include air monitoring.
** Please review chapter 21 for additional details.
Designated First Aid Plan: All injuries no matter how minor must be reported to Consigli Superintendent immediately. The superintendent will then report all injuries to the CCC Safety Director. A fully stocked first aid ki and blood borne pathogens kit shall be maintained on the project site. Only properly trained personnel will administer first aid. Consigli Construction shall follow Site Safety Plan for first Aid. Report all incidents to the Safety Director.
** Please review chapter 1 and 27 for additional details.
Substance Abuse: As a condition of employment, all Consigli personnel are required to submit to a urinalysis test for determination of the presence of illegal substances. A positive result will disqualify the applicant for employment on this project.
Emergency Management Response: In the event of an Emergency the construction workers shall leave all of the buildings immediately. Point of assembly/muster shall be at the designated location at the Consigli Field Office (as identified on the posted evacuation plan). In the Event of a DISASTER, the Superintendent or Safety director shall instruct the construction workers to leave the site or remain in place and await further instruction. The following steps should be taken in the event of an emergency
When reporting an emergency, please provide the following:
• Your location (refer to site evacuation plan) phone number, and name;
• The location of the incident (building name, floor and room number);
• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.);
• The name and amount of the material spilled (if applicable);
• The safest route to the spill (if applicable).
** Please review chapter 8 for additional details.
Minimum Site Safety Requirement: All Consigli workers, and any subcontractors, shall have, at a minimum, an OSHA 10 Hour Construction Safety Outreach training certificate and shall provide documentation of training.
Personnel Protective Equipment (PPE): All CCC and sub contractor workers will wear hard hats and safety glasses at all times. All CCC personnel performing work with their hands shall be required to wear gloves that are appropriate to the task. When not performing actual work with their hands workers will be required to have them available for immediate use. Face shields will be required for all personnel who are performing overhead work, using metal chop saw or any type of metal grinding. All welders will be required to have hard hats with integral welding shields.
Restricted Areas: Contractors are prohibited from entering adjacent occupied areas unless work has been previously authorized and scheduled. Only designated workers will be allowed into the occupied areas. No exceptions. All workers will try to limit their impact on surrounding areas.
Steel Erection: Steel workers will be required to use fall protection at 6′. Consigli will release documentation when column footings reach 75% of breaking strength. The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations. Decks will only be turned over for general use after they have undergone an inspection by a member of the CCC safety department.
The steel erection sub will be required to submit a detailed erection sequencing plan that illustrates crane locations and capacity of cranes at those locations. Fall protection will be determined for connectors after pre-construction meeting with sub is held. Fall protection will be required at 6’, at all times during steel erection
Once decking is complete and all required fall protection is installed, CCC will walk the area with the steel erection subcontractor. Provided all required elements of fall protection are in place, CCC will complete and give a copy of the “custody of fall protection” form to the steel erection subcontractor. Maintenance and overall responsibility of the fall protection system will fall to CCC.
Materials Management: Materials management, getting materials into and out of the project, will be done through existing entryways. Getting materials into and out of the project will be a challenge that needs to be adequately planned. All deliveries are to be scheduled with the CCC Superintendent. A comprehensive Activity Hazard Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed in a reasonable amount of time will be delivered to the site. Attention must be paid to structural analysis in regard to loading elevated existing floors with material and equipment. A material hoist will be located within the building.
Lean requirements/Materials Management/Housekeeping: Getting materials into and out of the project will be a challenge that needs to be adequately planned. All deliveries are to be scheduled with the CCC Superintendent. Deliveries will be made to Gate 1 on Commercial Street and only as scheduled. A comprehensive Activity Hazard Analysis shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed within three days’ time will be delivered to the site. Attention must be paid to structural analysis in regard to loading existing floors with material and equipment. Movement of all materials over 8ft. will require 2 workers.
Listed below are additional Lean requirements
- No materials shall be delivered to the site earlier than 3 days before said materials are to be installed/put into place. If materials have to be delivered before that 3 day time period, subcontractor shall get prior approval from Consigli Superintendent. Because of this, notification / scheduling is required for all deliveries to the site. Subcontractors must notify Contractor at least 24 hours in advance. Contractor has the right to refuse any deliveries not properly scheduled or due to logistical constraints as necessary.
- All subcontractors’ delivered materials shall be placed on wheeled carts, wheeled racks or in wheeled bins so as to necessitate easy relocation in the event materials need to be moved. Carts, racks, or dollies shall not exceed manufacturers intended weight loads. Materials/tools can be delivered and stored on pallets only if pallet jacks are delivered simultaneously with said delivery to provide for ready mobility. Additionally, pallet jacks need to remain in immediate area. Each subcontractor will need to supply their own pallet jacks for their own materials and keep their pallet jack within reasonable distance at all times.
- All work stations shall be provided with wheeled trash bins for immediate placement of all debris produced as a part of the subcontractor’s operations. All trash will be immediately placed in wheeled containers provided by Consigli.
- All subcontractors shall use rubber wheeled carts when moving material or removing trash from a building. Any damage caused by the Subcontractor shall be repaired at the cost of the Subcontractor. Back charges will be appropriately assessed for the cost of the repairs. No trash or materials shall be left on the floor.
- Subcontractors shall, where feasible, elevate all electrical extension cords, hoses, or cables– removing them from all walking/working surfaces. Electrical Cords, when elevated shall be supported or suspended in a manner that does not subject them to damage.
- Storage of delivered materials in cardboard containers shall be discouraged. When materials must stay in cardboard containers, said containers shall be removed from the projects immediately after product is unpacked.
- Subcontractor will participate in schedule development meetings as required by Consigli.
Environmental Issues: A hazardous material report was created by Abatement Professionals. This report will be on site at all times and available for review at any time.
Back– End of Site Safety Plan
Environmental Emergency Contact and Management Response
Consigli identified Emergency Response Subcontractor;
Name: Cyn Environmental Services, Inc. # (800) 242-5818
100 Tosca Drive Stoughton, MA 02072.
Asbestos: A Hazardous Materials report has been prepared by Abatement Professionals Inc. (EH&E) for Hobson’s Landing and is available in the Consigli Field Office for review. No asbestos was identified.
This does not mean that asbestos could not still be found in other areas (i.e. behind walls, mechanical chases, or under walls) caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately. All identified asbestos will be fully abated by a licensed and regulated asbestos abatement contractor under a formal plan to be written, submitted and in accordance with the DEP.
IT IS THE RESPONSIBILITY OF ALL SUBCONTRACTOR FOREMEN TO REVIEW THE HAZOUDOS MATERIAL REPORT & CORRESPONDING ABATEMENT REPORT WITH THEIR WORKERS. A copy of the hazardous Material/abatement report will be on site at all times and available to anyone request it.
Due to the fact that some asbestos may remain in place and not be abated during construction all workers will need to have at a minimum Asbestos awareness training.
All work and disposal will be done in compliance with state and federal regulations and standards
Lead: For renovation projects, all panted surfaces both interior and exterior of the existing must be considered lead containing, unless tested and show as otherwise. There is also lead in the soil. Consigli workers who will need to perform work on these painted surfaces may need to disturb this paint by drilling, sawing, demo, fastening, or carpentry. In doing so they will use saws, drills, screw guns, impact wrenches, sawzalls, hand wrenches, ads, crowbars, hammers, and other hand tools. Consigli Construction does posses historical data to show that drilling, sawing, light demo, installation of hangers, hanging sheetrock, fastening, and carpentry do not put the employee above the action level. Despite this additional monitoring will be done. An exposure assessment will be done by all subcontractors who disturb any painted surface or disturb/excavate soil. This does not mean that lead could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately. All workers on this must have completed Lead Awareness training prior to starting on this project. Hand wash stations will be provided to ensure proper hygiene during the project. An exposure assessment will also be done for any task which will disturb any lead containing material.
Silica: Any activity which can produce silica dust will use engineering controls to keep dust to a minimum. A written exposure plan must be developed for all silica producing tasks that clearly defines the following:
1) A description of the tasks in the workplace that involve exposure to respirable crystalline silica;
2) A description of the engineering controls, work practices, and respiratory protection used to limit employee exposure to respirable crystalline silica for each task;
3) A description of the housekeeping measures used to limit employee exposure to respirable crystalline silica; and
4) A description of the procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to respirable crystalline silica and their level of exposure, including exposures generated by other employers.
There will be no dry cutting of any masonry material allowed; if water cannot be used then a dustless vacuum system consisting of HEPA dustless vacuum system will be used. Prior to the project going full scale an exposure assessment of a worker grinding and cutting masonry while using the HEPA system an exposure assessment will be done so as to establish the silica exposure level. No respirators will be issued without the express consent of the Consigli Safety department. Nuisance mask like an N95 if used will be on a voluntary basis and at no time will these types of mask be issued to the workers.
Polychlorinated Biphenyl’s (PCBs): At this time there are no activities which are planned which would disturb any surface with suspect amounts of PCB’s… This does not mean that regulated levels of PCB’s could not still be found in other areas, caution must be used when working and if any workers identify any potentially hazardous substances then they should stop and notify their supervisor immediately.
Light ballast unless labeled “No PCB’S” will be designated PCB containing, All PCB containing material shall be removed and disposed of in accordance with all local, state (MEMEP Special waste management rules 06-096-CMR 400) and federal regulations and be coordinated with the building owner. All other inquiries or locations in regard to PCB containing material can be located in the Hazardous Material survey. If identified on any of the materials to be impacted, PCBs will be abated. Any and all PCB remediation will be performed by a licensed /qualified contractor
** Please review chapter 29 for additional details
Freon/Glycol: All Freon/Glycol materials will be removed from equipment and stored per manufacturer’s recommendations before it is disturbed, moved or removed. All workers who will be working with the above-mentioned materials must provide CCC with certifications or qualifications. If not re-used, a disposal manifest will be provided to CCC.
Mold: Mold issues are not anticipated to be prevalent on this project, however if mold is discovered Consigli’s mold remediation policy will be implemented and followed.
** Please review chapter 22 for additional details
Arsenic: Elevated levels of Arsenic have been found in the existing soil on site. As a precaution and exposure assessment will be performed during excavation operations to ensure levels a are below OSHA permissible exposure levels. These results will be attached to the V-Wrap which is located in the field office and available for review at any time.
** Please review V-Wrap for additional details
Noise: Noise exposure will be a concern, so all operations must be coordinated with the Consigli Superintendent to limit any excess noise impact on the surrounding areas. All activities and tasks which may cause loud noise will be monitored and building occupants will be notified of locations and dates/times of potential elevated noise levels.
**Please review chapter 29 for additional details
Equipment issues: All operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the State of ME. All safety devices and warning alarms must be in good working order and all leaks are to be repaired immediately. All equipment will be used in accordance with the manufacturer’s recommendations for safe usage and have its operator’s manual as well as an extinguisher with it at all times.
Adjacent Property: All steps will be taken to limit the effects of the project on the surrounding community. Special attention will be paid to each access point of each building so as not to impede access. Vibration and survey point monitoring will be required along retaining wall.
Exposure to Street Traffic: All deliveries will be made at a designated location unless otherwise directed by Superintendent. There will be exposure to live vehicular traffic and flaggers will be used when required. All speed limits will be obeyed, and deliveries will be made as to not coincide with buildings scheduled deliveries. All traffic control signage (if needed) will meet City of Portland requirements before being installed. Coordination with them as well as its police will be required when any equipment will be set up/used in the street/parking lot. Fire department access will be maintained and kept open for emergency responders.
Utility Exposures: All utilities entering the site will be cut and prior to the start of demolition. There are no overhead power line hazards. Written notification of this work will be provided to CCC prior to commencement of Demolition work.
Planning: The project team as well as CCC safety department will meet with each subcontractor, before they start to review their Site-Specific Safety and Health Program and all project specific Job Hazard Analyses. The project team shall be an integrated mix of owner, architect, engineer and Consigli Construction personnel. If, after reviewing programs and meeting with the individual subcontractor, the team is satisfied with the risk control direction, they will be permitted to begin work.
Exposure to the Visitors, Neighbors, and Occupants: During all phases of construction pedestrian walkways around the project will be open and occupied. Some areas of project will be opened for construction at different times. Any pedestrian walkway under any type of scaffold or overhead hazard will be provided with overhead protection. At no time is any worker allowed to enter any of the adjacent buildings.
Fraternization between construction employees and project owners, staff, or visitors will not be permitted. Loud and profane language or clothing with offensive language will not be allowed on the jobsite. Extra efforts must be made to keep noise to a minimum.
Safety Orientation Signature Page:
Project: Hobson’s Landing Project # 1882
I have viewed the Safety Orientation video and understand the Site Specific elements of the project as presented by Consigli Superintendent. I understand that I have access to any Hazardous Materials Reports and Safety Data Sheets for any hazardous substances that I may use. I understand that if I do not have necessary training that it is my responsibility to notify my supervisor immediately
Hobson’s Landing Site Specific Safety Orientation Briefing
Project Name: Hobson’s Landing
Project Number and Address: Job 1882 – 383 Commercial Street – Portland, ME
Project History: Former site of the Rufus Deering Lumber Yard in place for 160 years
Project Scope: Construction of a new 7 story residential condominium building which includes:
- Demolition of the Rufus Deering storage sheds, barns, and outbuildings
- Site Improvements including drainage and stabilization of the existing site and seawall
- New building to be steel structure with cast in place concrete decks.
- New building façade will be a combination of brick, fiber cement panel, windows, and curtainwall
Evacuation plan will be such that three long blasts of an air horn signal workers to leave the building and muster outside the Consigli office (former Rufus Deering Lumber Yard Office)
Parking will not be provided onsite nor is it allowed on the surrounding streets to site, contractors employees must utilize off-street parking.
Break areas will be via subcontractor storage trailers only
Site access will be via one of the two gates located on Commercial Street
Site was tested and cleared for Asbestos, however it is assumed that all existing outbuildings contain lead and lead based paints and materials will need to be handled as such.
Hot work permits will be issued by Consigli
Back– End of Environmental Emergency Contact and Management Response