Evacuation Plan

MGB Salem ASC

30 Rockingham Park Blvd. Salem, NH 03079

(Project # 2243)

An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire).  Person/persons discovering emergency shall take the following actions:

  • Immediately dial 911
  • Contact Consigli Superintendent: Todd Flanders (774)217-2349

Evacuation order shall be:

  • Alerting all workers by the sounding of three long blasts of an air horn or building alarm.
  • Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
  • Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
  • Portable fire extinguishers are provided if fire is in incipient phase only.
  • The Superintendent, or any other trained individual on site, may perform first aid on any injured person once safely outside evacuated area.
  • After an emergency evacuation, employees are directed to gather at the site trailers at the corner of the project site (see photo below)
  • Superintendent Michael Caputo, or a CCC designee, will be responsible for accounting for all CCC employees on site.
  • Superintendent Michael Caputo, or the CCC designee, will be responsible for knowing which subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Michael Caputo or the CCC representative.
  • For further assistance with emergency evacuation procedures, you may contact Safety Director Bryan Kingsbury at (508)808-9359.

Muster Point

Back End of Evacuation Plan and Muster Point