Evacuation Plan

Raytheon Pod C – Project # 2651

An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire).  Person/persons discovering emergency shall take the following actions:

Evacuation order shall be:   

  • Alerting all workers by the sounding of three long blasts of an air horn or building alarm.
  • Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
  • Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
  • Raytheon facilities will notify Tim Sampson or CCC designee of incoming Med flight so any potential obstructions can be lowered to the ground.
  • Portable fire extinguishers are provided if fire is in incipient/budding phase only.
  • Superintendent, Tim Sampson, and any other trained individual on site, is responsible for performing first aid on any injured person once outside evacuated area.
  • After an emergency evacuation, employees are directed to the gather at the corner of the building located in the parking area. (See Evac)
  • Tim Sampson, or a CCC designee, will be responsible for accounting for all CCC employees on site.
  • Superintendent Tim Sampson, or the CCC designee, will be responsible for knowing which subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Tim Sampson or the CCC representative. For further assistance with emergency evacuation procedures, you may contact Safety Director Dan Della-Giustina at (508)686-6008.

Muster Point

BackEnd of Evacuation Plan and Muster Point