Evacuation Plan

NYU Langone Huntington – 789 Park Ave., Huntington, NY  11743

An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire).  Person/persons discovering emergency shall take the following actions:

  • Immediately dial 911
  • Contact Consigli – Superintendent – Chris Caulfield

Project Manager – Geoff Schwartz

Project Executive – Vencent Fiorella

Regional Safety Manager – Shawn Kenney

Evacuation order shall be:

  • Alerting all workers by the sounding of three long blasts of an air horn.  
  • Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
  • Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
  • Portable fire extinguishers are provided if fire is in incipient/budding phase only.  No employee is required to fight a fire.
  • After an emergency evacuation, employees are directed to gather across from the main entrance
  • Chris Caulfield will be responsible for accounting for all Consigli employees on site.
  • Superintendent Chris Caulfield, or the Consigli designee, will be responsible for knowing what subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Chris Caulfield or the Consigli representative.

Muster Point

Back End of Evacuation Plan and Muster Point