MSK LINAC & XRAY – 650 Commack Rd., Commack, NY 11725
An evacuation will be ordered for life threatening emergencies (collapse, explosion, fire). Person/persons discovering emergency shall take the following actions:
- Immediately dial 911
- Contact Consigli – Superintendent – Jeff Van Schaick
Project Manager – Geoff Schwartz
Project Executive – Vencent Fiorella
Regional Safety Manager – Shawn Kenney
Evacuation order shall be:
- Alerting all workers by the sounding of three long blasts of an air horn.
- Workers must stop and secure all work and machinery, including all hoisted materials, and evacuate the building immediately by use of the nearest exit.
- Critical operations shutdown procedures (unless listed above) are not required, because no employees are authorized to delay evacuation for this purpose.
- Portable fire extinguishers are provided if fire is in incipient/budding phase only. No employee is required to fight a fire.
- After an emergency evacuation, employees are directed to gather near the construction dumpster
- Jeff Van Schaick will be responsible for accounting for all Consigli employees on site.
- Superintendent Jeff Van Schaick, or the Consigli designee, will be responsible for knowing what subcontractors are on site at all times. A representative from each subcontractor will be responsible for accounting for their employees and notifying Jeff Van Schaick or the Consigli representative.
Muster Point
Back– End of Evacuation Plan and Muster Point