Site Specific Safety and Health Program

Brighton High School Lab Renovation

Project # 2975

25 Warren Street, Brighton MA

 

 

Emergency Response Plan

SITE INFORMATION

This Emergency Response Plan (E.R.P.) is specifically developed for Consigli Construction work associated with the BHS Lab Reno project.

SITE LOCATION

The construction site is located at 25 Warren Street, Brighton MA.The location for the project field office will be the trailer complex located near the entrance to the site (notifications of any changes will be provided).  Unless otherwise determined, the field office will become the Emergency Operations Center (EOC).

EMERGENCY TYPE

The following situations are considered emergency response actions and should be handled in accordance with the procedures outlined in this plan.

    • Serious Injury/Fatalities

    • Fire/Explosion

    • Structural Damage/Collapse

    • Weather or Geological Event

    • Environmental Incident

    • Traffic Disruption

    • Utility Damage

    • Illegal Activity

    • Labor Problems

    • Bomb Threats/Military Ordinance Unearthing

    • Acts of Terrorism

The following is a list of the Chain of Command/Call Hierarchy for establishing lines of succession during communication involving all emergencies.

Back End of Emergency Response Plan

 

 

Emergency Contact Names and Numbers

1. First call: 911

2. CCC Superintendent: Tom Ciampa (508)686-0462

3.CCC PM: Aaron Champagne (508)735-9531

4. CCC Project Executive: Ernie Vrahopoulos (617)620-3974

5. CCC Safety Director: Bryan Kingsbury (508)808-9359

6. CBRE Director Greg Sowyrda (781)292-0331               
                                                                                          

Additional Consigli Construction Contacts:

    • CCC Safety Manager: Dan Della-Giustina    

    • CCC General Super: Tom Smith

Brighton

Boston Police Department (Non-Emergency) (617)343-4260

Brighton Fire Department- (Non-Emergency) (617)343-2880

Brighton Public works-(24 hr. emergency) (617)635-7507

NSTAR Gas (800)572-9300

NSTAR Electric (800)592-2000

Telephone-Verizon-(local) (800)870-9999

Note: If any utility is struck/damaged, 911 must be called immediately!

                                           Environmental Consultant

Cashins and Associates

Mike Cashins (781)389-7170

599 North Ave #8 Wakefield MA, 01880

Back End of Emergency Contact Names and Numbers

 

 

Medical Facilities

OHST Total Care

(866)510-3002 / Fax  (617)663-6677

1340 Soldiers Field Road Brighton, MA 02135

Mass General Hospital (Non-Emergency)

(617)726-2000

55 Fruit Street Boston, MA 02114

Emergency Response and Rescue

In the event of an emergency the following policy will be adhered to for the safe evacuation of the Project. An immediate call will be made to 911.  Project information for the call is – 25 Warren Street, Brighton MA. (Note:  If calling from a cell phone you will be reaching the State Police and not the local emergency response)

A Consigli representative will be dispatched to the Main entrance of the site (or work area, as necessary) to meet the responding Emergency Personnel and advise the individual in charge of the location of any chemicals or hazardous substances that may be present on any of the floors. Safety Data Sheets will be provided if needed by the Fire Dept.

In the event of a serious injury requiring the assistance of EMS the injured worker will be kept as comfortable as possible.  Emergency first aid, if necessary, will be administered.  Under no circumstances will the injured person be moved unless the worker’s life is in danger because of fire or calamity.  A worker will be assigned to meet the medical personnel at the above location to direct them to the location of incident.

In the event an evacuation is required all personnel at this job site will follow the building/site evacuation plan and meet at the designated Muster Point located within the project site fence. (see evac). The foreman for each company will meet at that location and take a head count of their staff and report to Consigli Superintendent. If for some reason a worker is unaccounted for, the fire department will be notified of the last location where the worker was observed.

Back End of Medical Facilities

 

 

Site Safety Plan

Scope of Proposed Operations: The project will begin in late June 2023 and will end in August 2023.  Project hours will be between 7:00am and 3:30pm Monday through Friday. There will be roughly 15– 25

workers at the height of construction.

This scope of work will be a renovation of labs within the existing Brighton High School with a total of five classrooms,

Demolition/ Abatement : old floor tiles, sub flooring, old lab benches, light fixtures

Installing: New water heaters, painting walls, installing emergency stations (showers), new lab benches, running conduit, and new piping for cold water.

MEPs will be adjusted as needed for the new construction scope.

PURPOSE: The purpose of this Site-Specific Safety and Health Program is to illustrate Consigli’s approach to identifying project specific hazards and controls and how said risk is managed through a comprehensive Safety and Health Program.

S.A.F.E.: Staying Accident Free Every Day is the Safety Mission that forms the very foundation of the Consigli Safety Culture.  The S.A.F.E.  mission, which is supported by technology, (Predictive Solutions internal auditing instrument  which identifies and defines leading indicator related information); Leadership (Empowering our team members to assure safe projects); Humanization (Protect the ones you love by protecting yourself); Jobsite Gym (Morning warm-ups, jobsite gym); Training (Integrating sub-contractors into the Consigli Safety Culture); and Lean (nothing hit the ground), is the driving force behind Consigli’ s drive to our vision – ZERO.  ZERO is the philosophy that all accidents are preventable, and that no accident is acceptable.  The S.A.F.E. mission is the guiding force to achieving the Consigli Safety Vision which is ZERO.  

Post Incident Review: Any CCC incident that results in a recordable injury will require a post incident review. The worker who was injured along with their foreman/Safety Personnel/PM/Sup/etc… will need to fill out Appendix?? (Post incident review form) and attend this meeting. At this meeting they will re-emphasize their commitment to safety, determine chronology of events, identify contributing factors, identify root cause, provide improvement plan to prevent reoccurrence and discuss disciplinary actions taken (if any). Findings from this meeting will be shared/disseminated with all contractors on site and other CCC projects to prevent reoccurrence.

Contractor Orientation:  All workers on-site must complete the Consigli site orientation training by watching a video and displaying the orientation sticker on their hardhat once orientation is complete.

Identify the specific route in and out of the construction site (Traffic Management): Main construction access will be restricted to routes pre-determined by Consigli. All contractors will be responsible for adhering to CCC restrictions and regulations in regard to driving and delivering materials. All material and debris will process through the laydown yard located at the entrance of the project. The public will be given the right of way at all times. Parking will not be provided

Designated work hours (any work outside these hours must have prior CCC approval):  All work shall take place during business hours, Monday – Friday 7:00am to 3:30pm, any work which may need to take place outside of these hours will need to be approved by the CCC Superintendent.

Demolition:  Prior to the start of demo operations, the contractor preforming demo will confirm that all utilities leading into the area have been made safe.  The electrician will disconnect and lock out all electrical, the plumber will do the same with any plumbing lines, and the HVAC subcontractor will do the same on the HVAC piping and duct work.  Lock out tag out will be reviewed during the pre-construction safety meetings to assure disconnect and responsibility for protection of existing utilities is safe for any construction activities to commence. In spaces where some electrical or mechanical must remain live, a color coding system will be utilized for easy identification of live utilities that must stay active and utilities that must be removed.  Any and all utilities spay painted Red are not to be touched and need to be protected during all operations. Utilities spray painted Green are to be removed as part of the selective demolition process only after lock-out/tag-out has been confirmed and utilities tested.  If any utilities are unmarked, they shall be considered live.  The demo contractor will be responsible for completing CCC demo checklist prior to the start of any work in their target areas.

    • A plumber will be responsible for confirming that all Gas service to the  building has been adequately cut and capped by Eversouce.

    • Baseline air samples will be conducted by an IH in part of a fugitive dust prevention plan. This will also include frequent and regular air sampling around the projects fence line to assure dust emissions are adequately controlled.

    • The demo subcontractor will be responsible for conducting an engineering survey of the building to be demoed prior to work beginning.

    • All dust control methods will be the responsibility of the demolition subcontractor.

Noise: Noise exposure will be a concern, so all operations must be coordinated with the Consigli Superintendent to limit any excess noise impact on the surrounding areas. All activities that create loud noises are to be coordinated with Consigli and Ownership. This and other noise restrictions will be shared with each worker during site orientation.

** Please review chapter 29 for additional details.

Exposure to the Visitors, and the public: During all phases of construction, the buildings and pedestrian walkways in the surrounding area will be open and occupied.  Access routes used by the workers for moving materials and debris will be communicated to the workers and updated as needed.  At no time is any worker allowed to enter any of the adjacent occupied building/spaces unless they have received approval from CCC.  Non-fraternization with visitors or the public will be stressed with all subcontractor personnel during orientations. 

Activity Hazard Analysis (AHA):  An AHA/JHA depending on level of hazard shall be conducted for each identifiable feature of work to be performed.  The AHA/JHA shall be submitted to Consigli superintendent/supervisor.  AHA/JHA shall be reviewed weekly, signed by all workers including their supervisor, with all involved personnel performing that particular task.

Excavations:  All required permitting will be obtained before any excavating is to begin, tabulated data/engineering for shoring and shielding systems will be on site at all times when in use. Written excavation inspections will be done daily.

            1. Dig Safe Notification.

            2. City/town (dpw or town hall) or campus permits requirements if needed.

            3.  Jackie’s law permitting has been obtained.

            4.  All road plates that will be in pedestrian walkways will be slip resistant

Workers preforming site work will be make sure to remove all underground tanks mentioned in site report per all MA and state guidelines.

Fall Protection:  All workers exposed to a fall of 6′ or greater shall be protected by guardrails safety nets or personnel fall arrest systems.  this include, but is not limited to, steel erection, roofing, scaffold erection and dismantling, overhand brick laying and pre-cast concrete related work.  Holes greater than 2” will be covered with acceptable material (3/4 plywood ½ steel) which will be secured and marked hole and capable of supporting 2x the intended load (cover must be able to withstand 2x times the intended axle load).  Covers will stay in place until the hole/penetration has been filled with duct or Pipe riser which extends above the deck. Building perimeters (to be protected with cable guard rail system with turnbuckles to be installed for all straight runs and any straight run over 100 feet.  Before any work is to begin on the roof it must be determined what method of fall protection will be implemented All workers working on a roof with a slope greater than 4 to 1 and exposed to a fall greater than 6 feet will have fall protection 100%of the time spent in this location.  Workers on a roof with a slope less than 4 to 1 may put flagging (six feet for roofers-15 feet for everyone else) lines up, whenever roofers and any other trade are on the same roof then the flagging must be pulled back to the maximum distance.  All subcontractors will be responsible for barricading/taping off areas below their elevated work.  The use of safety Monitors is not allowed!

**Review Chapter 13 for more detail

Roof Work: Before any work is to begin on the roof it must be determined what sections of the roof will be worked and what method of fall protection will be implemented. Attention will be paid to any access points located below elevated work. If present, they will be protected.  (100% tie off, guard rails, flagging etc. the use of safety monitors is not allowed)

Work on Ladders: All work on step ladders/straight ladders will be done correctly per manufacturer’s recommendations.  Any worker who is on a step/straight ladder and could be exposed to a fall greater than the height of their work on the ladder will be required to install a form of fall protection.  Step ladders will not be used as a form of access to a walking /working level, also all straight ladders will be tied of when installed for use.  Only ladders with a rating Type 1A or 1AA will be allowed on Consigli projects.

Scaffold and elevated work platforms:  All scaffolds supported frame, pipe staging, and Aerial lift platforms will be inspected daily before each shift by a competent person designated by each individual contractor who will be using it, which will be documented on Inspection tags located at the stair tower to each section… A scaffold checklist will be provided by CCC to each sub contractors designated persons to aid them with their daily inspection. All contractors who will be erect scaffold will provide CCC with certification/Qualification of scaffold erection training as well as an erection/dismantling plan. Fall protection is required 100% during erection/dismantling. Overhead protection will be provided for all access points at any buildings which are located under any form of scaffolding. Fall protection is required at 6’ on all scaffolds, on mobil scaffold fall protection is required at 4’. Mobil staging with a work platform with a height to base ratio greater than two to one will require outriggers.

** Please review chapter 14 for additional details.  

Aerial/Scissor Lifts: If lifts are required, the area and ground conditions, in the intended work area, will be inspected for overhead power lines, sink holes, covers, or any other unsafe conditions which cause an unsafe incident.  Aerial lift platforms will be inspected daily before each shift by a competent person designated.  All who will be performing work from an aerial lift will show documented proof of training prior to using the lift.  Steel plates or equipment mats will be placed on the ground above any utility/ steam tunnel if there will be Aerial lifts operating on them. Workers will be tied off at all times when using an aerial lift.

Global Harmonization:  All Materials and chemicals used on-site will have Safety Data Sheets (SDS) provided before being brought onsite.

    • SDS sheets on file in Consigli Construction’s Site Safety Plan

    • All SDS sheets shall be readily accessible.

** Please review chapter 20 for additional details.   

Fire Protection: An NFPA 241 plan has been written to encompass all phases of work. This plan will designate FPPM and Alternate FPPM. Hot work is anticipated, and efforts will be made to reduce the need for on-site hot work.   If, however, any hot work is required the Consigli hot work permit program will be implemented.   This will be coordinated through Consigli Construction, building staff and local Fire department. (If needed).   All hot work will stop one hour before the regular end of the day work stoppage.   Flammables will not be stored inside the building or left overnight on the scaffold or in the building.  All combustible or flammable materials will be stored in an appropriately rated lockable cabinet located no closer than 50 feet from the nearest structure. Fire extinguishers will be provided for every 3000 square feet.  They will be installed on job made stands and conspicuously located throughout.  They will be part of the daily inspection with extinguisher log completed monthly.  Storage of any acetylene cylinders will be done in a secure and upright area, with good ventilation.  This will be a strict no smoking project. All penetrations leading outside of the construction area will be fire stopped using approved fire rated material prior to the end of each shift. All workers who pull a Hot work permit with CCC will need to provide a NFPA hot Work Training Certificate.

**Review Chapter 17 for more detail.

Electrical: All electrical tools, cords and equipment must be in good working order. To that end, all electrical tools and components must be visually checked on a daily basis.  Any tools with damaged cords or damaged cords must be taken out service… All cords must be equipped with a ground pin, flat three wire cords are not allowed.  SJO and SJT or other similarly rated cords only shall be used.  The electrician will be responsible for all temp power and any temp lighting that may be needed.  They will coordinate all lock out tag out procedures. All temporary power for the project will be installed on protected and dedicated circuits with 100% GFCI protection.  GFCI will be tested by the electric contractor weekly to assure proper function with a logbook filed with CCC monthly.  No live electrical work will be conducted.

**Review Chapter 26 for more detail

Utility Exposures:  Any overhead power lines will be located and identified prior to use of any equipment which may come in to contact with them… All sidewalks will be protected if equipment is to be driven over them

Cranes:  There will be the use of cranes, including tower cranes throughout the duration of this project. Crane work plans must be submitted to the CCC safety Department prior to crane mobilization on-site.  This work plan must also include the FAA criteria letter of determination with regards to crane proximity to flight lines/helipads. There is a requirement to assure that certified riggers, signalmen, evaluation letter and crane assemblymen are utilized.  All picks are to be done by a licensed operator.  As previously mentioned, a detailed pick plan will be required to assure that no picks are critical in nature.  Critical picks are defined as those involving 2 cranes lifting simultaneously, a pick that is over 75% of capacity, a pick that involves the lifting of a man basket, over an occupied area or any other lift that is deemed to involve special conditions.  Location and set up will be reviewed with crane operator prior to set up and pick.  All lifting operations will require that the operator and any involved contractors follow the steps listed below as well as in CCC Crane Safety policy.

 1. All Hoisting equipment will have an up-to-date 3rd party inspection certificate with the equipment which will be copied and filed in the office trailer.

2. All lattice boom cranes will have an independent 3rd party inspection completed each time one is set up on the project, after assembly and prior to operation.

3. All equipment operators will be required to have in their possession all appropriate licensing and training as required by OSHA and the Commonwealth of MA.

4. All underground vaults and existing utilities will be marked before as well as before any crane is set up.

5. Documented rigging equipment inspections.

6. Documented daily crane inspections filed with CCC weekly.

7. Documented rigger and hand signalman training will be provided.

8. Letter from the owner of the crane stating that the worker has been evaluated and they are competent in the operation of the crane they will be using on site.

** Please review chapter 24 for additional details.  

Confined Space:  There may be potential to enter the existing mechanical crawl space in the basement for mechanical and electrical installations.  This space must be thoroughly analyzed for confined space hazards and a plan created if entry is required.

** Please review chapter 21 for additional details.   


Designated First Aid Plan:
  All injuries no matter how minor must be reported to Consigli Superintendent immediately. The superintendent will then report all injuries to the CCC Safety Director.  A fully stocked first aid kit and blood borne pathogens kit shall be maintained on the project site.  Only properly trained personnel will administer first aid.  Consigli Construction shall follow Site Safety Plan for first Aid.  Report all injuries/incidents regardless how minor to CCC immediately

** Please review chapter 1 and 27 for additional details.  

Substance Abuse: As a condition of employment, all Consigli personnel are required to submit to a urinalysis test for determination of the presence of illegal substances.  A positive result will disqualify the applicant for employment on this project.

Evacuation Plan (RACE, and Routes of Egress): Please refer to the Evacuation Plans attached.  All Consigli employees shall attend the Project Safety Orientation.  Consigli Construction’s Job Supervisor will conduct a safety orientation talk to each employee and subcontractor to site specific fire safety protocols.

Emergency Management Response: In the event of an Emergency the construction workers shall leave all the buildings immediately. Point of assembly/muster shall be located outside the field office trailer located at the entrance to the site (as identified on the posted evacuation plan).  In the Event of a DISASTER, the Superintendent or Safety director shall instruct the construction workers to leave the site or remain in place and await further instruction.  The following steps should be taken in the event of an emergency.

When reporting an emergency, please provide the following:

• Your location ( 25 Warren Street, Brighton MA) phone number, and name.

• The location of the incident (building name, floor, and room number).

• Nature and extent of the incident (injury, accident, spill, smoke/fire, damage, etc.).

• The name and amount of the material spilled (if applicable); and

• The safest route to the spill (if applicable).

**Call Safety Director Bryan Kingsbury (508)808-9359**

** Please review chapter 8 for additional details.  

 Minimum Site Safety Requirement:  All Consigli workers, and any subcontractors, shall have, at a minimum, an OSHA 10 Hour Construction Safety Outreach training certificate and shall provide documentation of training.

 Personnel Protective Equipment (PPE):  All CCC and sub-contractor workers will always wear hard hats and safety glasses.  All CCC personnel performing work with their hands shall be required to wear gloves that are appropriate to the task.  When not performing actual work with their hand’s workers will be required to have them available for immediate use.  Face shields will be required for all personnel who are performing overhead work, using metal chop saw or any type of metal grinding.  All welders will be required to have hard hats with integral welding shields.

Site Security: Site security will be maintained through numerous systems throughout the life of the job. Construction fencing will be provided around the site per approved CMP plan. Fencing will include scrim, and signage outlining basic construction rules. Gates will be locked during non-working hours.  Off-hours security details will be utilized during the final (6) months of construction.

Restricted Areas:  Contractors are prohibited from entering any adjacent areas of the campus unless work has been previously authorized and scheduled.  It is important that workers do not park in/in front of adjacent driveways during construction or for deliveries.  All workers will try to limit their impact on surrounding areas.

Lean requirements/Materials Management/Housekeeping: Getting materials into and out of the project will be a challenge that needs to be adequately planned.  All deliveries are to be scheduled with the CCC Superintendent.  A comprehensive JSA shall be done on all materials that will be hoisted and placed into the building. Only materials which will be used/installed within three days’ time will be delivered to the site. Attention must be paid to structural analysis in regard to loading floors with material and equipment. Movement of all materials over 8ft. will require 2 workers.

Listed below are additional Lean requirements.

    • No materials shall be delivered to the site earlier than 3 days before said materials are to be installed/put into place.  If materials must be delivered before that 3-day time period, subcontractor shall get prior approval from Consigli Superintendent.  Because of this, notification / scheduling is required for all deliveries to the site. Subcontractors must notify Contractor at least 24 hours in advance. Contractor has the right to refuse any deliveries not properly scheduled or due to logistical constraints as necessary.

    • All subcontractors’ delivered materials shall be placed on wheeled carts, wheeled racks or in wheeled bins so as to necessitate easy relocation in the event materials need to be moved.  Carts, racks, or dollies shall not exceed manufacturers intended weight loads.  Materials/tools can be delivered and stored on pallets only if pallet jacks are delivered simultaneously with said delivery to provide for ready mobility.  Additionally, pallet jacks need to remain in immediate area.    Each subcontractor will need to supply their own pallet jacks for their own materials and always keep their pallet jack within reasonable distance.

    • All workstations shall be provided with wheeled trash bins for immediate placement of all debris produced as a part of the subcontractor’s operations.  All trash will be immediately placed in wheeled containers provided by Consigli.

    • All subcontractors shall use rubber wheeled carts when moving material or removing trash from a building.  Any damage caused by the Subcontractor shall be repaired at the cost of the Subcontractor.  Back charges will be appropriately assessed for the cost of the repairs.  No trash or materials shall be left on the floor. 

    • Subcontractors shall, where feasible, elevate all electrical extension cords, hoses, or cables – removing them from all walking/working surfaces.  Electrical Cords, when elevated shall be supported or suspended in a manner that does not subject them to damage. 

    • Storage of delivered materials in cardboard containers shall be discouraged.  When materials must stay in cardboard containers, said containers shall be removed from the projects immediately after product is unpacked. 

    • Subcontractor will participate in schedule development meetings as required by Consigli

Back End of Site Safety Plan

 

 

Environmental Emergency Contact and Management Response

Consigli identified Emergency Response Subcontractor

Name: Cynn Environmental Services, Inc. (781)341-1777

100 Tosca Drive Stoughton, MA 02072 

Asbestos: Hazardous Materials report has been prepared and is in the field office and is available for review at any time. Asbestos has been identified in the following but not limited to gray pipe insulation, Brown floor tile, and black floor tile mastic. This does not mean it is not present or could be found at a later date or location. At no time, shall a worker disturb any material he/she cannot readily identify.  If they come across a material, he/she cannot confirm as Asbestos free, they shall notify their supervisor immediately. A complete list of ACMs and their location can be found in the hazardous material report which will be filed in the office and available for review at any time.  ACM that will need to be abated will be done so by a MA licensed asbestos contractor.   

    •  This list and complete Hazardous Materials Report will be available on site all times.  

It is the responsibility of all subcontractor foremen to share this report with their respective workers.

Lead: A hazardous material report has not been completed by the owner. All existing painted surfaces will be presumed lead containing. A Haz Mat report which will be in the field office and available for review. A TCLP will be required to be produced by the demolition sub that meets a representative sample of the debris being thrown in the dumpster.

    1. All subcontractors will be required to perform exposure assessments for any planned tasks on painted surfaces identified as having lead paint…

    1. Any work on lead paint related building components (stairway rails) will require workers to have lead awareness training before any work is done.

    1. Consigli workers may need to perform work on the original Building surfaces.  They may need to disturb this paint by drilling, sawing, demo, fastening, or carpentry.  In doing so they will use saws, drills, screw guns, impact wrenches, Sawzall’s, hand wrenches crowbars, hammers, and other hand tools.

    1. Consigli construction does possess historical data to show that drilling, sawing, light demo, installation of hangers, hanging sheetrock, fastening and carpentry do not put the employee above the action level.  Despite this, additional monitoring may be done if needed.

    1. Consigli or subcontractor workers performing activities other than those listed above must be monitored to insure they are not being exposed to a hazard.

    1. Consigli employees will be provided with Tyvek suits and gloves at their request.

    1. If paint flakes or dust is generated from lead paint, then the area must be cleaned using HEPA vacuums or wet washing using TSP.  Areas should not be dry swept.  They may be swept using a sweeping compound as long as lead dust is not made airborne and other methods are infeasible.

    1. Workers who contact potential lead paint or other contaminated surfaces should use proper hand and face washing procedures prior to eating, drinking, smoking, chewing tobacco, chewing gum, or applying cosmetics.  A hand wash station will be established and maintained for the project duration.

    1. Subcontractor foremen are responsible for reviewing hazmat reports with their employees and ensuring their compliance with the safety rules. All workers on this project must have completed Lead awareness training prior to starting on this project.

    1.  A hand wash station will be established and maintained for the project duration.

Silica: Any activity which can produce silica dust will use engineering controls to keep dust to a minimum.  A written exposure plan must be developed for all silica producing tasks that clearly defines the following:

1) A description of the tasks in the workplace that involve exposure to respirable crystalline silica.

 2) A description of the engineering controls, work practices, and respiratory protection used to limit employee exposure to respirable crystalline silica for each task.

 3) A description of the housekeeping measures used to limit employee exposure to respirable crystalline silica.

 4) A description of the procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to respirable crystalline silica and their level of exposure, including exposures generated by other employers.

 There will be no dry cutting of any masonry material allowed; if water cannot be used then a dustless vacuum system consisting of HEPA dustless vacuum system will be used.  Prior to the project going full scale an exposure assessment of a worker grinding and cutting masonry while using the HEPA system an exposure assessment will be done so as to establish the silica exposure level.  No respirators will be issued without the express consent of the Consigli Safety department.  Nuisance mask like an N95 if used will be on a voluntary basis and at no time will these types of masks be issued to the workers.

Mold: Mold issues are not anticipated to be prevalent on this project, however if mold is discovered Consigli’s mold remediation policy will be implemented and followed.

** Please review chapter 22 for additional details.

Mercury: All fluorescent lamps are presumed to contain mercury vapor, which is a hazardous substance. Mercury-containing lamps associated with fluorescent light fixtures in areas designated to be renovated will be treated accordingly.  All florescent bulbs removed during renovation will be collected and be recycled or disposed of properly.

Freon/Glycol:  All Freon/Glycol materials will be removed from equipment and stored per manufacturer’s recommendations before it is disturbed.  All workers who will be working with the above-mentioned materials must provide CCC with certifications or qualifications.  If not re-used, a disposal manifest will be provided to CCC.

 Exposure to the Visitors, Staff, Students and Public: During all phases of construction pedestrian walkways around the project will be open and occupied. Some areas of project will be opened for construction at different times.  Any pedestrian walkway under any type of scaffold or overhead hazard will be provided with overhead protection. At no time is any worker allowed to enter any of the adjacent buildings. 

Fraternization between construction employees and project owners, staff, the public or visitors will not be permitted.  Loud and profane language or clothing with offensive language will not be allowed on the jobsite. Extra efforts must be made to keep noise to a minimum

Additional Controls: Prior to start of any work, all personnel involved in the project, including project managers must be:

    1. Trained and orientated by Consigli Construction.  Stickers will be issued and displayed on hard hats.

Planning:  The project team will meet with ownership and Environmental Safety & Health (EHS) staff before the project start to review any site-specific safety and health requirements. The project team shall be an integrated mix of owner, architect, engineer, and Consigli Construction personnel.

Safety Spot Recognition Plan: The purpose of this plan is to instantly recognize workers “on the spot” for working safely and to reward those workers immediately. This will assist CCC reduce the complacency of workers on all our projects. Members from the CCC and MH project teams (Supers, PM, APM, PE, OPM, Architect, Owners, etc..) will be provided with 5$ MH cafeteria gift certificates prior to their walk on site. They are to present these cards to workers who are working safely and or those taking additional steps to work safely. After issuing the card, the name and hard hat sticker number of the worker as well as a brief description of what they were doing will be documented in a log that will be maintained in the field office. This shall be completed at a minimum of twice a week. It is required that different field staff take turns in issuing the cards to workers in the field. Also required will be the communication of who is be recognized to other sub-contractors/workers through foreman meetings and daily stand ups. at the end of the project the sub-contractor who has had the most workers recognized will receive an appropriate acknowledgment from CCC as well as some type of reward that is to be determined by CCC field staff.

Back End of Environmental Emergency Contact and Management Response